郑州大学毕业设计
目: 40m预应力混凝土简支T型梁桥设计
(净-7+2×0.75m人行道)
指导教师: 李清富 职称: 教授
学生姓名: 张朋杰 学号: 20070510235
专 业: 水利水电工程(道路与桥梁方向)
院(系): 水利与环境学院
完成时间: 2011年6月
2011年 6月 1 日
摘 要
本设计从最基本的设计方法入手,重点进行了主梁的设计,掌握了主梁的设计方法,其它部分的设计就可以仿照主梁设计进行。
本设计的主要内容包括:纵横断面布置,主梁设计,横隔梁设计,还有行车道板设计。纵横断面布置:根据规范要求和工程实践经验确定主梁间距与主梁片数和主梁高度及各截面主要尺寸。主梁设计:内力计算由恒载内力和活载内力计算组成。恒载内力由结构力学可求出,而活载内力计算时要利用按修正偏心压力法计算得出的荷载横向分布系数。根据计算得出的各种内力组合确定设计控制内力进而对预应力钢束数进行估算。按后张法制作主梁,采用锥型锚具和直径50mm的抽拔橡胶管,计算各种预应力损失得出有效预应力,对主梁进行强度、应力和变形验算。横隔梁设计:设置横隔梁是为了保证各主梁共同受力和加强结构整体性,本设计中采用偏心压力法进行横隔梁计算。鉴于桥梁跨中处横隔梁受力最大,只计算跨中横隔梁内力,其余横隔梁可依据中横隔梁偏安全地选用相同的截面尺寸和配筋。行车道板设计:本设计中行车道板的受力图示为单向板。
关键词:T形梁;预应力;混凝土桥
ABSTRACT
This design begins with basic method and gives most content to the design of main beams. When the method of main beams designing is mastered, we can go on the designing of other parts.
The main content of this design is as followings: The arrange of longitudinal section and lateral section, Main beams design, Crossing beam designing and Drive-way plank designing.The arrange of longitudinal section and lateral section:According to the specification and the experience of practical engineering, we can decide the distance of girders, the number of the girders, the height of the main beams and the main size of each section.Main beams design: Internal forces include invariable force and variable force. We can use the method of the structural mechanics. To calculate the variable internal force, we calculate the lateral direction coefficient of the load with the method of corrected eccentricity pressures.with the result of the calculation, we can obtain the control internal force, and we can approximately decide the number of the pre-stressed concrete band.design the main beams with post-tensioning method, selecting pre-burry corrected tube anchoring. Then calculate the loss of the pre-stress and obtain the valid pre-stress and examine the strength, stress, and transform of the main beams.Crossing beam designing:To make sure that all main beams rear the load together and to enhance the globality of the construction, this design goes on the crossing beam calculation with the method of corrected eccentricity pressures. We only calculate the internal force of the middle crossing beam because of the maximum force is in the place of the middle of the span. Drive-way plank designing:In this design, the force diagram of the drive-way plank is single direction plank.
Key words: T-beam;pre-stress;concrete bridge.
目 录
I
摘 要
II
ABSTRACT
1
第1章 纵横截面布置
1
1.1 设计目的
1
1.2 基本资料
2
1.3 主梁间距与主梁片数
4
1.4 主梁跨中界面尺寸拟定
5
1.5 横截面沿跨长的变化
5
1.6 横隔梁的设置
6
第2章 主梁计算
6
2.1 恒载内力计算
6
2.1.1 恒载集度
7
2.1.2 恒载内力
7
2.2 活载内力计算(修正刚性横梁法)
7
2.2.1 冲击系数和车道折减系数
8
2.2.2 计算主梁的荷载横向分部系数
12
2.2.3 车道荷载的取值
15
2.3 主梁内力组合
15
2.4 预应力钢束的估算及其布置
15
2.4.1 跨中截面钢束的估算和确定
17
2.4.2 预应力钢束布置
22
2.5 计算主梁截面几何特性
22
2.5.1 净截面几何特性计算
22
2.5.2 换算截面几何特性计算
23
2.5.3 有效分布宽度内截面几何特性计算
24
2.5.4 各阶段截面对形心轴的静矩计算
26
2.6 钢束预应力损失计算
27
2.6.1 预应力钢束与管道壁之间的摩擦损失
28
2.6.2 由锚具变形,钢束回缩引起的损失
30
2.6.3 混凝土弹性压缩引起的损失
31
2.6.4 由钢束应力松弛引起的损失
31
2.6.5 混凝土收缩和徐变引起的损失
34
2.6.6 预加内力计算即钢束预应力损失汇总
36
2.7 主梁截面承载力与应力验算
37
2.7.1 持久状况承载能力极限状态承载力验算
41
2.7.2 持久状况构件的应力验算
49
2.7.3 短暂状况构件的应力验算
50
2.8 主梁端部的局部承压验算
54
2.9主梁变形验算
54
2.9.1 计算由预加应力引起的跨中反拱度
56
2.9.2 计算由荷载引起的跨中挠度
57
2.9.3 结构刚度验算
57
2.9.4 预拱度的设置
58
第3章 横隔梁计算
58
3.1 确定作用在跨中横隔梁的可变作用
58
3.2 跨中横隔梁的作用效应影响线
59
3.2.1 绘制弯矩影响线
61
3.2.2 绘制剪力影响线
62
3.3 截面作用效应计算
63
3.4 截面配筋计算
65
第4章 行车道板计算
65
4.1 悬臂板荷载效应计算
67
4.2 荷载效应组合
68
4.3 截面设计、配筋与承载力验算
70
结束语
71
参考文献
72
致 谢
73
中英文翻译
第1章 纵横截面布置
1.1 设计目的
通过设计,全面掌握公路预应力公路桥梁的设计过程,培养和运用所学专业知识的能力。达到能适应桥梁工程施工、设计和管理的基本要求水平。
1.2 基本资料
(1)桥面跨径及桥宽净空
跨径:
(墩中心距离);
计算跨径:
(支座中心距离);
主梁全长:
(主梁预制长度);
桥面净空:净—7
+2×0.75人行道
(2)设计荷载:公路—Ⅱ级,人群荷载3.0
2,人行道4.0
,护栏、栏杆的作用力为1.52
,防撞栏4.99
.
(3)材料及工艺:混凝土:主梁用C40,人行道、栏杆及桥面铺装用C20。
预应力钢筋束:采用
标准的
碳素钢丝,每束由24丝组成。普通钢筋:直径大于等于12mm的用
钢筋,直径小于12mm的均用热轧R235光圆钢筋。钢板及角钢:制作锚头下支撑垫板、支座垫板等均用普通A3碳素钢,主梁间的联接用
低合金结构钢板。
工艺:按后张工艺制作主梁,采用45号优质碳素结构钢的维形锚具和直径50mm抽拔橡胶管。
(4)基本计算数据
1 基本计算数据表
名 称
项 目
符 合
单位
数据
混
凝
土
立方强度
R
MPa
40
弹性模量
Eh
MPa
3.3×104
轴心抗压标准强度
MPa
28.0
抗拉标准强度
MPa
2.60
轴心抗压设计强度
Ra
MPa
23.0
抗拉设计强度
Rl
MPa
2.15
预施应力阶段
极限压应力
0.70
*
MPa
17.64
极限拉应力
0.70
*
MPa
1.638
使用荷载
作用阶段
荷载组合Ⅰ:
极限压应力
0.5
MPa
14.0
极限主拉应力
0.8
MPa
2.08
极限主压应力
0.6
MPa
16.8
荷载组合Ⅱ或组合Ⅲ:
MPa
极限压应力
0.6
MPa
16.8
极限主拉应力
0.9
MPa
2.34
极限主压应力
0.65
MPa
18.2
5
碳
素
钢
丝
标准强度
MPa
1600
弹性模量
Ey
MPa
2.0×103
抗拉设计强度
Ry
MPa
1280
最大控制应力σk
0.75
MPa
1200
使用荷载作用阶段极限应力:
荷载组合Ⅰ
0.65
MPa
1040
荷载组合Ⅱ或组合Ⅲ
0.70
MPa
1120
材料
容重
钢筋混凝土
r1
KN/m3
25.0
混凝土
r2
KN/m3
24.0
钢丝束
R3
KN/m3
78.5
钢束与混凝土的弹性模量比值
ny
无量钢
6.06
*注:本设计考虑主梁混凝土达90%标准强度时,开始张拉预应力钢束。
与
分别表示钢束张拉时混凝土的抗压,抗拉标准强度,则
1.3 主梁间距与主梁片数
1.3.1.主梁间距通常应随梁高与跨径的增大而加宽为经济,同时加宽翼板对提高主梁截面效率指标ρ很有效,故在许可条件下应适当加宽T梁翼板。但标准设计主要为配合各种桥面宽度,使桥梁尺寸标准人而采用统一的主梁间距。交通《公路桥涵标准图》中,钢筋混凝土和预应力混凝土装配式简支T形梁跨径
从16m到40m,主梁间距均为1.6m,考虑人行道适当挑出,净—7附2×0.75m的桥宽则选用五片主梁。
1.3.2.主梁跨中截面主要尺寸的拟定
(1)主梁高度
预应力混凝土简支桥桥梁的主梁高度与其跨径之比通常在1/15~1/25,标准设计中高跨比约在1/13~1/19。当建筑高度不受限制时,增大梁高往往是较经济的
,因为增大梁高可节省预应力钢束用量,同时梁高加大一般只是腹板加高,而混凝土用量增加不多。综上所述,标准设计中对于40m跨径的简支梁桥取用230cm的主梁高度是比较合适的。
EMBED AutoCAD.Drawing.17 图1 结构尺寸图(尺寸单位:cm)
(2)主梁截面细部尺寸
T梁翼板的厚度主要取决于桥面承受车轮局部荷载的要求,还应考虑能否满足主梁受弯时上翼板受压的强度要求。本示例预制T梁的翼板厚度取用10cm,翼板根部加厚到22cm以抵抗翼缘根部较大的弯矩。为使翼板与腹板连接和顺,在截面转角处设置圆角,以减少局部应力和便于脱模。
1.4 主梁跨中界面尺寸拟定
在预应力混凝土梁中腹板内因主拉应力甚小,腹板厚度一般由布置制孔管的构造决定,同时从腹板本身的稳定条件出发,腹板厚度不宜小于其高度的1/15,标准图的T梁腹板厚度均取16cm。
马蹄尺寸基本由布置预应力钢束的需要确定的。设计实践表明,马蹄面积占截面总面积的10~20%为合适。本示例考虑到主梁需要配置较多的钢束,将钢束按三层布置每层排三束,同时还根据《桥规》互6、2、26条对钢束净距及预留管道的构造要求,初拟马蹄宽度36cm,高度38cm。马蹄与腹板交接处做成45°斜坡的折线钝角,以减少局部应力。如此布置的马蹄面积约占整个截面积的18%。
按照以上拟定的外形尺寸,就可绘出预制梁的跨中截面布置图(见图2)。
图2 跨中截面尺寸图(尺寸单位:mm)
(1). 计算截面几何特征
将主梁跨中截面划分成五个规则图形的小单元,截面的几何特性列表计算见表2。
(2).检验截面效率指标
上核心距:
下核心距:
EMBED Equation.3
表2 核心距计算结果
分
块
名
称
分块面积
Ai(cm2)
分块面积形至上缘距离
(cm)
分块面积至缘静矩
(cm3)
分块面积的自身惯矩Ii
(cm4)
di=ys-yi
(cm)
分块面积对截面形心的惯矩IX=Aidi2(cm4)
I=Ii+ IX
(cm4)
翼板
1264
4
5056
6741
87.5
9669981
9676722
三角
支撑
852
12
10224
6816
79.5
5380248
5387064
腹板
3104
105
325920
9735179
-13.5
568557
10303736
下三角
100
198.7
19867
556
-107.2
1149205
1149761
马蹄
1368
211
288648
65856
-124.5
21034368
21323016
∑
6328
578795
∑IT=42215926
注:截面效率指标:
EMBED Equation.3 =
>0.5
表明以上初拟的主梁跨中截面尺寸时合理的。
1.5 横截面沿跨长的变化
如图1所示,本设计主梁采用等高形式,横截面的T梁翼板厚度沿跨长不变,马蹄部分为配合钢束弯起而从跨径四分点附近开始向支点逐渐抬高。梁端部区段由于锚头集中力的作用而引起较大的局部应力,同时也为布置锚具的需要,在距梁端2060mm范围内将腹板加厚到与马蹄同宽。变化点截面(腹板开始加厚处)到支点的距离为2060mm,其中还设置一段长300mm的腹板加厚过渡段。
1.6 横隔梁的设置
模型试验结果表明,主梁在荷载作用位置的弯矩横向分布,在当该位置有横隔梁时比较均匀,否则主梁弯矩较大。为减少对主梁设计起主要控制作用的跨中弯矩,在跨中位置设置一道中横隔梁;当跨度较大时,还应在其它卫士设置较多的横隔梁。本设计在桥跨中、四分点、支点处共设置五道横隔梁,其间距为1097mm。横隔梁采用开洞形式,他的高度取2060mm平均厚度150mm,详见图1所示。
第2章 主梁计算
根据上述梁跨结构纵、横截面的布置,并通过活载作用下的梁桥荷载横向分布计算,可分别求得主梁隔控制截面(一般取跨中、四分点、变化点截面和支点截面)的恒载和最大活载内力,然后再进行主梁内力组合。
2.1 恒载内力计算
2.1.1 恒载集度
(1)预制梁自重
①按跨中截面计,主梁的恒载集度:
②由于马蹄抬高形成四个横置的三棱柱,折算成恒载集度为:
③由于腹板加厚所增加的重量折算成恒载集度为:
④边主梁的横隔梁中横隔梁体积:
⑤端横隔梁体积:
故:
⑥预制梁恒载集度:
(2)二期恒载,栏杆及铺装
一侧栏杆:
人行道板:
铺装:
若将两侧人行道板、栏杆均摊给5片主梁,则:
2.1.2 恒载内力
如图3所示,社x为计算截面离左支座的距离,并令
。
图3 永久作用计算效应计算图
主梁弯矩和剪力的计算公式分别为:
恒载内力计算见表3。
表3 1号梁永久作用效应
跨 中
四 分 点
变化点
支 点
一
期
弯矩(kN·m)
4462.6
3348.73
799.70
0
剪力(kN)
0
203.39
368.55
406.79
二
期
弯矩(kN·m)
2045.8
1535.2
366.6
0
剪力(kN)
0
93.24
169.0
186.5
2.2 活载内力计算(修正刚性横梁法)
2.2.1 冲击系数和车道折减系数
按《桥规》4.3.2条规定,结构的冲击系数与结构的基频有关,因此要先计算结构的基频。简支梁桥的基频可采用下列公式估算:
其中:
根据本桥的基频,可以计算出汽车荷载的冲击系数为:
按“桥规”规定,当车道当车道数多于两道时,需进行车道折减,三车道折减
,四车道折减
,本次是双车道不需考虑车道折减系数为1。
2.2.2 计算主梁的荷载横向分部系数
(1)跨中的荷载横向分布系数
如前所示,本例桥跨内设五道横隔梁,具有可靠的横向联系,且承重结构的长宽比为:
所以可以按修正的刚性横梁法来绘制横向影响线并计算横向分布系数
.
①计算主梁抗扭惯矩IT
对于T形梁截面,抗扭惯矩可近似按下式计算
式中:
和
———相应为单个矩形截面的宽度和高度;
———矩形截面的抗扭刚度系数;
———梁截面划分成单个矩形截面的个数。
对于跨中截面,翼缘板的换算平均厚度:
马蹄部分的换算平均厚度:
图4示出了IT的计算图式,IT的计算见表4
图4 IT计算图式(尺寸单位:mm)
表4 IT计 算 表
分块名称
bi (cm)
ti (cm)
bi/ ti
ci
ITi=ci×bi×ti(×10-3m4)
翼缘板①
160
16
0.0875
0.333
1.5267
腹 板②
183
16
0.0874
0.333
2.4935
马 蹄③
36
43
0.9167
0.1527
2.4675
∑
6.6877
②.计算抗扭修正系数β
主梁间距相同,同时将主梁近似的看成等截面,则得:
式中:
;
;
;
;
;
;
;
;
计算得:
。
③按修正的刚性横梁计算横向影响线竖向影响线竖坐标值:
式中:
,
=
。
计算所得的
值列于表5内。
表5 计算所得的
值
梁 号
1
3.2
0.5482
0.0259
-0.1482
2
1.6
0.3741
0.1130
0.0259
3
0
0.2
0.2
0.2
④计算荷载横向分布系数。
1号梁横向影响线和最不利布载图式如图4-5所示。
1、2、3号梁的横向分布系数
1号梁:
2号梁:
3 号梁:
图6 支点的横向分布系数mo计算图式(尺寸单位:cm)
(2) 支点截面的何在横向分布系数
如图6所示,按杠杆原理法绘制荷载横向分布影响线并进行布载,1号梁可变作用的横向分布系数可计算如下:
可变作用(汽车):
可变作用(人群):
(3)横向分布系数汇总(见表6)
表6 1号梁可变作用横向分布系数
可变作用类别
公路-II级
0.6216
0.4375
人群
0.5197
1.4219
2.2.3 车道荷载的取值
根据《桥规》4.3.1条,公路––I级的均布荷载标准值qk和集中荷载标准值Pk为:
计算弯矩时:
计算剪力时:
·2.2.4 计算可变作用效应
(1)求跨中截面的最大弯矩和最大剪力
计算跨中截面最大弯矩和最大剪力采用直接加载求可变作用效应,图4-7示出跨中截面作用效应计算图示,计算公式为:
式中:
—所求截面汽车(人群)标准荷载的弯矩或剪力;
—— 车道均布荷载标准值;
——车道集中荷载标准值;
——影响线上同号区段的面积;
---影响线上最大坐标值
可变作用(汽车)标准效应:
可变作用(汽车)冲击效应:
可变作用(人群)效应
EMBED Equation.3 (2) 求四分点截面的最大弯矩和最大剪力
图7四分点截面作用效应的计算图示。
可变作用(汽车)标准效应:
可变作用(汽车)冲击效应:
可变作用(人群)效应
(3) 求截面变化点的弯距和剪力
图7有变化点截面作用效应的计算图示。位置离支座中心2.06m。
可变作用(汽车)效应:
计算变化点截面汽车荷载产生的弯矩和剪力时,应特别注意集中荷载Pk的作用位置。集中荷载若作用在计算截面,虽然影响线纵坐标最大,但其对应的横向分布系数较小,荷载向跨中方向移动,就出现相反的情况。因此应对两个截面进行比较,即影响线纵坐标最大截面和横向分布系数达到最大值的截面,然后取一个最大的作为所求值。
通过比较,集中荷载作用在变化点为最不利情况,结果如下:
可变作用(汽车)冲击效应:
可变作用(人群)效应:
(4) 求支点截面的最大剪力
图7出支点截面最大剪力计算图示。
可变作用(汽车)效应:
可变作用(汽车)冲击效应:
可变作用(人群)效应:
2.3 主梁内力组合
本设计按《桥规》4.1.6~4.1.8条规定,根据可能同时出现的作用效应应选择了三种最不利效应组合:短期效应组合、标准效应组合和能力极限状态基本组合,见表7
表7 主梁作用效应组合
序号
荷载类别
跨中截面
四分点截面
变化点截面
支点
(kN·m)
(kN)
(kN·m)
(kN)
(kN·m)
(kN)
(kN)
(1)
第一类永久作用
3345.9
0
2510.7
172.1
671.8
307.7
344.2
(2)
第二类永久作用
999.6
0
750.1
51.4
200.7
91.9
102.8
(3)
总永久作用=(1)+(2)
4345.5
0
3260.8
223.5
872.5
399.6
447.0
(4)
可变作用(汽车)
2319
96
1739
193
383.7
204
212
(5)
可变作用(汽车)冲击
322
13.3
241.7
26.8
53.3
28.4
29.5
(6)
可变作用(人群)
265
6.3
272.8
17.8
61.1
28.2
40
(7)
标准组合=
(3)+(4)+(5)+(6)
9291.4
115.6
7045.1
528.7
1642.4
788.0
863.6
(8)
短期组合=(3)+0.7×
(4)+(6)
8273.7
73.5
6354.9
444
1474
698.4
770.5
(9)
极限组合=1.2×(3)+1.4×[(4)+(5)]+1.12 ×(6)
11756
160
8828.4
677
2039.4
989.8
1081.4
2.4 预应力钢束的估算及其布置
2.4.1 跨中截面钢束的估算和确定
根据《公预规》规定,预应力梁应满足正常使用极限状态的应力要求和承载能力极限状态的强度要求。以下就跨中截面在各种作用效应组合下,分别按照上述要求对主梁所需的钢束数进行估算,并且按这些估算的钢束数的多少确定主梁的配束。
(1).估算钢束数对于简支梁带马蹄的T形截面
按正常使用极限状态的应力要求
当截面混凝土不出现拉应力控制时,则得到钢束数n的估算公式:
式中: Mk—持久状态使用荷载产生的跨中弯距标准组合值,按表4-7取用;
Ci— 与荷载有关的经验系数,对于公路—Ⅱ级,
取用0.51;
△Ap—一股24
5钢绞线截面积,
故: △Ap =4.712
。
在第一章中已计算出成桥后跨中截
,初故
,则钢束偏心矩为
。
1号梁:
EMBED Equation.3
(2).按承载能力极限状态估算钢束数
根据极限状态的应力计算图式,受压区混凝土达到极限强度fcd,应力图式呈矩形,同预应力钢束也达到设计强度fcd,则钢束数的估算公式为:
EMBED Equation.3
式中:
—承载能力极限状态的跨中最大弯矩,按表4-7取用;
—经验系数,一般采用0.75~0.77,本算例取用0.76;
—预应力钢绞线的设计强度,见表4-1,为1280MPa。
计算得:
根据上述两种极限状态,取钢束数n=13
2.4.2 预应力钢束布置
2.4.2.1 跨中截面及锚固端截面布置
(1)对于跨中截面,在保证布置预留管道构造要求的前提下,尽可能使钢束群重心的偏心距大些,本算例采用直径50mm的抽拔橡胶管成型的管道,根据《公预规》6.2.26条规定,管道至梁底和梁侧净矩不应小于5cm,管道净距为40mm。根据以上规定,跨中截面的细部构造如图8)所示。由此可得出钢束群重心至梁底距离为:
(2)为方便张拉操作,将所有钢束都锚固在梁端,对于锚固端截面,钢束布置通常考虑下述两个方面:一是预应力钢束合力重心尽可能靠近截面形心,使截面均匀受压;二是考虑锚头布置的可能性,以满足张拉操作方便的要求。
图8 钢束布置图(尺寸单位:mm)
a);跨中截面; b);锚固截面
按照上述锚头布置的“均匀”、“分散”原则,锚固端截面所布置的钢束如图8b)所示。钢束群重心至梁底距离为:
为验核上述布置的钢束群重心位置,需计算锚固端截面几何特性。图9示出计算图示,锚固端截面特性计算见表8所示。
表8 钢束锚固截面几何特性计算表
分块名称
Ai
(cm2)
yi
(cm)
Si
(cm3)
Ii
(cm4)
Di=ys-yi
(cm)
Ix=Aidi2
(cm4)
I=Ii+Ix
(cm4)
翼板
1264
5
6320
7032
92.5
11039806
11046547
三角承托
628.3
11.5
7183
3703
86
4649394
4653096
腹板
7992
119
951048
32823144
-21.6
3709438
36532582
∑
9885
963287
52232225
其中:
故计算得:
cm
说明钢束群重心处于截面的核心范围内。
2.4.2.2 钢束起弯角及线形的确定
确定钢束起弯角时,既要照顾到由其弯起产生足够的竖向预剪力,又要考虑到所引起的摩擦预应力损失不宜过大。为此,本算例将端部锚固端截面分成上、下两部分(见图4-10),上部钢束的弯起角定为10°,下部钢束弯起角定为7.5
为简化计算和施工,所有钢束布置的线形均为直线加圆弧,并且整根钢束都布置在同一个竖直面内。
图9 钢束群重心位置复核图式
图10 封锚端混凝土块尺寸图
2.4.2.3 钢束计算
(1)计算钢束起弯点至跨中的距离
锚固点到支座中心线的水平距离axi(见图c)为:
EMBED Equation.3
其余表中直接给出方法一样,不再赘述
图11示出钢束计算图示,钢束起弯点至跨中的距离
列表计算在表9内。
图11 钢束计算图式(尺寸单位:mm)
(2)控制截面的钢束重心位置计算
①各钢束重心位置计算
由图11所示的几何关系,当计算截面在曲线段时,计算公式为:
其中:ai—钢束在计算截面处钢束重心到梁底的距离;
ao—钢束起弯前到梁底的距离;
R—钢束弯起半径
②计算钢束群重心到梁底距离
表9 各计算截面的钢束位置及钢束群重心位置
截面
钢束号
x4
(cm)
R
(cm)
Sina= x1/R
cosa
a0
(cm)
a1
(cm)
四分点
N1(N2)
未弯起
-
—
—
7.5
7.5
N12
890.5
10264-
0.0754
0.9972
25.5
54.3
变化点
N1(N2)
107.02
2628.5
0.0388
0.9993
7.5
9.5
N12
1537
10264
0.1507
0.9886
116.2
141.6
支点
N1(N2)
313.1
2628.5
0.1172
0.9931
7.5
25.6
N12
1743.5
10264
0.1709
0.9853
25.5
175.2
表 10 各钢束在各个变化点距底部距离
钢束号
跨中
(cm)
四分点
(cm)
变化点
(cm)
支点
(cm)
锚固点
(cm)
N1(N2)
7.5
7.5
9.47
25.61
30
N3(N4)
16.5
16.5
34.4
55.9
60
N5(N6)
25.5
25.5
62.9
86.5
90
N7(N8)
34.5
34.5
105.3
126.8
130
N9
7.5
15.1
64.7
86.2
90
N10
16.5
24.7
91.4
126.5
130
N11
25.5
43.0
120.3
149.5
155
N12
34.5
63.4
148.6
175.3
180
N13
43.5
87.1
169.1
200.9
205
(3)钢束长度计算
一根钢束的长度为曲线长度、直线长度与两端工作长度(2×70cm)之和,其中钢束的曲线长度可按圆弧半径与弯起角度进行计算。通过每根钢束长度计算,就可得出一片主梁和一孔桥所需钢束得总长度,以利备料和施工。计算结果见表11所示。
表11 各钢束总长度计算结果
钢束号
R
(cm)
钢束弯起角度
曲线长度(cm)
S
直线长度xi(见表9)(cm)
有效长度
2(S+xi+Li)(cm)
钢束预留长度(cm)
钢束长度
(cm)
N1(N2)
2628.5
7.5
344.1
1885.9
4462
140
2*4602.0
N3(N4)
5081
7.5
665.2
1563.4
4457.3
140
2*4597.3
N5(N6)
7535.0
7.5
986.3
1239.0
4450.6
140
2*4590.6
N7(N8)
7863.5
10
1371.7
861.8
4467.1
140
2*4607.1
N9
7483.2
7.5
984.6
1241.0
4451.3
140
4591.3
N10
8064.5
10
1407.5
829.1
4473.3
140
4617.3
N11
9117.8
10
1591.4
642.8
4468.5
140
4608.5
N12
10171.1
10
1775.2
456.6
4463.7
140
4603.7
N13
11224.5
10
1959.0
270.5
4459.1
140
4599.1
2.5 计算主梁截面几何特性
本节在求得各验算的毛截面特征和钢束位置的基础上,计算主梁净截面和换算截面的面积、惯性距及梁截面分别对重心轴、上梗肋与下梗肋的静矩,最后汇总成截面特征植总表,为各受力阶级的应力验算准备计算数据。
现以跨中截面为例,说明其计算方法,在表12中亦出其它截面特征值的计算结果。
2.5.1 净截面几何特性计算
在预加应力阶段,只需要计算小截面的几何特征。
计算公式如下:
截面积
截面惯矩
计算结果见表13。
2.5.2 换算截面几何特性计算
在使用荷载阶段需要计算大截面(结构整体化以后的截面)的几何特性,计算公式如下:
截面积
截面惯矩
其结果列于表12
以上式中 :
----分别为混凝土毛截面面积和惯矩;
----分别为一根管道截面面积和钢束截面积;
----分别为净截面和换算截面重心到主梁上缘的距离;
----分面积重心到主梁上缘的距离;
----计算面积内所含的管道(钢束)数; 跨中翼缘全宽截面面积和惯矩计算表
表12 跨中翼缘全宽截面面积和惯矩计算表
----钢束与混凝土的弹性模量比值;由表1得
截面
分块名称 Lp=Aidi2
分块面积 Ai(cm2)
分块面积重心至上缘距离 yi(cm)
分块面积对上缘静矩 si(cm)
全截面重心到上缘距离 ys(cm)
分块面积的自身惯矩
Ii(cm4)
di
Lp=Aidi2(cm4)
I=∑Ii+∑Ip(cm4)
b1=158cm
净截面
毛截面
6528
92
578796
87.6
50135763
-3.85
89350
38286552
扣管道面积(
)
-256.4
211.7
-41576
略
-124.1
-3941637.
5771.6
—
537228
50135763
—
-3852287
b1=160cm
换算截面
毛截面
6528
92
578795
94.7
50135763
4.1
103467
59796673
钢束换算面积 (aEp-1)n△Ap
1289.3
211.7
50479
略
-116.1
17344784
7717.3
—
629338
50135763
—
17580747
计算截面
△A= 19.635(cm2) n=13根 aEp=6.06
2.5.3 有效分布宽度内截面几何特性计算
根据《公预规》4.2.2条,预应力混凝土梁在计算预应力引起的混凝土应力时,预加力作为轴向力产生的应力按实际翼缘全宽计算,由预加力偏心引起的弯矩产生的应力按翼缘有效宽度计算。因此表 中的抗弯惯矩应进行折减。由于采用有效宽度方法计算的等效法向应力体积和原全宽内实际的法向应力体积是相等的因此用有效宽度截面计算等代法向应力时,中性轴应取原全宽截面的中性轴。
(1)有效分布宽度的计算
根据《公预规》4.2.2条,对于T形截面受压区翼缘计算宽度bf′,应取用下列三者中的最小值:
故:
=160cm
(2)有效分布宽度内截面几何特性计算
由于截面宽度不折减,截面的抗弯惯矩也不需折减,取全宽截面值。
2.5.4 各阶段截面对形心轴的静矩计算
预应力钢筋混凝土梁在张拉阶段和使用阶段都要产生剪应力,这两个阶段的剪应力应该叠加。在每一个阶段中,凡是中和轴位置和面积突变处的剪应力,都是需要计算的。例如,张拉阶段和使用阶段的截面,除了两个阶段a-a和b-b位置的剪应力需要计算外,还应计算:
图12 静矩计算图式(尺寸单位:mm)
(1)在张拉阶段,净截面的中和轴位置产生的最大剪应力,与使用阶段在净截面的中和轴(简称净轴)位置产生的剪应力叠加;
(2)在使用阶段,换算截面的中和轴(简称换轴)产生的最大剪应力,与张拉阶段在换轴位置的剪应力叠加。
因此,对于每一个荷载作用阶段,需要计算四个位置(共8种)的剪应力,因此需要计算下列几种情况的截面净矩:
①a-a线以上(或以下)的面积对中性轴(净轴和换轴)的静矩;
②b-b线以上(或以下)的面积对中性轴(净轴和换轴)的静矩;
③净轴(n-n)以上(或以下)的面积对中性轴(净轴和换轴)的静矩;
④换轴(0-0)以上(或以下)的面积对中性轴(净轴和换轴)的静矩;
计算结果列于表13
表13 跨中截面对重心轴静矩计算
分块名称及
序号
静矩类别及符号
分块面积Ai(cm2)
分块面积重心至全截面重心距离Ai (cm)
对净轴*静矩Si-j= Ai·yi(cm3)
静矩类别及符号
Ai
(cm)
yi
(cm)
对换轴*静矩
(cm3)
翼板①
翼缘部分
1320
83.6
94989
翼缘部分
1340
91.6
105544
三角承托②
对净轴
852
75.6
64425
对换轴
852
83.6
71235
肋部③
静矩
320
77.6
24837
静矩Sa-o
320
85.6
27395
∑
(cm3)
----
----
184251
(cm3)
----
----
204174
下三角④
马蹄部分对净轴净矩
100
111
11100
马蹄部分对换轴静矩Sb-o(cm3)
100
103
10300
马蹄⑤
1368
128.4
129411
1368
120.4
121354
肋部⑥
160
109.4
17501
160
101.4
16223
管道或钢束
-196.4
124.1
-24364
238.4
116.1
-27682
∑
----
----
133752
----
----
175565
翼板①
净轴以上净面积对净轴净矩
94988
净轴以上换算面积对换轴静矩Sn-o(cm3)
105534
三角承托②
64425
71235
肋部③
1401.8
43.8
61413
1529.8
47.8
73129
∑
----
----
220826
----
----
249898
翼板①
换轴以上净面积对净轴净 矩
94988
换轴以上换面积对换轴静矩
So-o(cm3)
105534
三角承托②
64425
71235
肋部③
1529.7
39.8
60902
1401.9
51.8
72618
∑
----
----
220315
----
----
249387
其它截面特性值均可用同样方法计算,下面将计算结果列表如表14
表14 主梁截面特性值总表
名称
符号
单位
截面
跨中
四分点
变化点
支点
混凝土净截面
净面积
An
cm2
6528
6528
6985
9637
净惯矩
In
cm4
39286553
39742164
46754584
52000521
净轴到截面上缘距离
yns
cm4
87.6
87.9
90.1
96.8
净轴到截面下缘距离
ynx
cm
142.4
142.0
130.8
133.2
截面抵抗矩
上缘
Wns
cm3
448376
452687
471568
537654
下缘
Wnx
cm3
275927
279736
357287
390365
对净轴静矩
翼缘部分面积
Sa-n
cm3
184230
184952
210865
201854
净轴以上面积
Sn-n
cm3
220567
221489
260054
310248
换轴以上面积
So-n
cm3
220355
221456
259687
310654
马蹄部分面积
Sb-n
cm3
133652
138955
237456
--------
钢束群重心到净轴距离
en
cm
124.1
114.0
57.9
34.7
混凝土换算截面
换算面积
Ao
cm2
7717.5
7717.5
7942.4
11138
换算惯矩
Io
cm4
49658725
49153645
50790608
58647822
换轴到截面上缘的距离
yos
cm4
95.6
95.3
102.4
98.1
换轴到截面下缘的距离
yox
cm
134.4
134.7
127.6
1319
截面抵抗矩
上缘
Wos
cm
477695
474022
471677
536577
下缘
Wox
cm3
339541
335129
378258
399458
对换轴静矩
翼缘部分面积
Sa-o
cm3
204164
203343
219857
205504
净轴以上面积
Sn-o
cm3
249989
248651
275456
323733
换轴以上面积
So-o
cm3
175565
170243
252945
马蹄部分面积
Sb-o
cm3
116.1
106.7
54.3
33.4
钢束群重心到截面下缘距离
en
cm3
18.3
28.1
81
106
2.6 钢束预应力损失计算
根据《公预规》6.2.1条规定,当计算主梁截面应力和确定钢束的控制应力时,应计算预应力损失值。后张法梁的预应力损失包括前期预应力损失(钢束与管道壁的摩擦损失,锚具变形,钢束回缩引起的损失,分批张拉混凝土弹性压缩引起的损失)和后期预应力损失(钢绞线应力松弛,混凝土收缩和徐变引起的应力损失),而梁内钢束的锚固应力和有效应力(永存应力)分别等于张拉应力扣除相应阶段的预应力损失。
预应力损失值因梁截面位置不同而有差异,现以四分点截面(既有直线束,又有曲线束通过)为例说明各项预应力损失的计算方法。对于其它截面均可用同样方法计算,它们的计算结果均列入钢束预应力损失及预加内力一览表内
2.6.1 预应力钢束与管道壁之间的摩擦损失
按《公预规》6.2.2条规定,计算公式为:
式中:
——张拉钢束时锚下的控制应力;根据《公预规》6.1.3条规定,对于钢绞线取张拉控制应力:
——钢束与管道壁的摩擦系数,对于预埋波纹管取
;
——从张拉端到计算截面曲线管道部分切线的夹角之和(rad);
——管道每米局部偏差对摩擦的影响系数,取
;
——从张拉端到计算截面的管道长度(m),可近似取其在纵轴上的投影长度(如图-14),当四分点为计算截面时,
。
表15 四分点截面管道摩擦损失
计算表
钢束号
(rad)
(m)
(MPa)
N1(N2)
0.1309
10.07
0.0871
0.0834
100.8
N3(N4)
0.1309
10.03
0.0870
0.0833
99.96
N5(N6)
0.1309
9.9915
0.0870
0.0833
99.96
N7(N8)
0.1201
9.9507
0.0809
0.0819
98.28
N9
0.1250
10.0951
0.0840
0.0809
97.16
N10
0.1197
10.0854
0.0809
0.0819
98.28
N11
0.1110
9.0413
0.0761
0.0735
88.24
N12
0.0992
9.9972
0.0705
0.0677
81.24
N13
0.0894
9.9531
0.0641
0.0621
74.52
2.6.2 由锚具变形,钢束回缩引起的损失
根据《公预规》
计算公式如下:
式中:
—— 锚具变形、钢束回缩值(mm) 取12mm
—— 预应力钢束有效长度。
四分点截面
的计算结果见表16
表16 四分点截面
的计算结果
钢束号
L
N1(N2)
44620
53.79
N3(N4)
44573
53.84
N5(N6)
44506
53.93
N7(N8)
44671
53.93
N9
44513
53.92
N10
44733
53.65
N11
44685
53.71
N12
44637
53.77
N13
44591
53.82
表17 四分点截面
计算表
钢
束
号
锚固时预加纵向力
(0.1KN)
(见表
10)
(cm)
(N·m)
(N·m)
计算应力损失的钢束号
(MPa)
N13
1071.66
5029.25
5029
55.0
276608
276608
N12
0.77
0.53
1.3
7.88
N12
1057.11
4929.20
9958
78.6
387435
664043
N11
1.53
1.65
3.18
19.30
N11
1038.79
4843.77
14802
99
479533
1143577
N10
2.27
3.38
5.65
34.24
N10
1013.83
4727.38
19529
117.3
554521
1698098
N9
3.00
5.43
8.43
51.08
N9
997.92
4700.2
24229
127
596925
2295024
N8
3.71
6.21
9.93
60.18
N8
987.81
4650.58
28882
107.5
500152
2795176
N7
4.42
7.56
11.98
72.6
N7
975.39
4594.09
33476
107.5
493864
3289041
N6
5.13
9.65
14.78
89.57
N6
956.54
4505.3
37981
116.6
525318
3814359
N5
5.82
11.19
17.01
103.08
N5
943.03
4441.7
42423
116.6
517902
4332262
N4
6.5
13.7
20.2
122.4
N4
922.6
4345.4
46769
125.6
545782
4878044
N3
7.16
15.4
22.56
136.7
N3
910.3
4287.5
51056.5
125.6
538510
5416554
N2
7.82
18.34
26.16
158.5
N2
898.5
4231.9
55288
134.6
569613
5986167
N1
8.46
20.27
28.73
174.1
N1
882.5
4156.5
59444
134.6
559464
6545632
表18 四分点截面
计算表
计算数据
计算
EMBED Equation.DSMT4
⑴
⑵
⑶=⑴+⑵
9.1
9.4
18.5
计算应力损失
计算公式:
分子项
分母项
(4)
247
60887.3
(5)
46
3.14
(6)
0.9[(4)+(5)]
262
0.714%
1.23
2.6.3 混凝土弹性压缩引起的损失
后张法梁当采用分批张拉时,先张拉的钢束由于张拉后批钢束产生的混凝土弹性压缩引起的引力损失,根据《公预规》6.2.5条规定,计算公式为:
式中:
——在先张拉钢束中心处,由后张拉各批钢束而产生的混凝土法向应力,可按下式计算:
其中
EMBED Equation.3 ——分别为钢束锚固时预加的纵向力和弯矩,
——计算截面上钢束重心到截面净轴的距离,
;
本算例采用逐根张拉钢束,预制时张拉钢束N1~N13,张拉顺序为N1~N13 顺序张拉。计算时应从最后张拉的一束逐步向前推进。
2.6.4 由钢束应力松弛引起的损失
《公预规》5.2.11条规定,对于作超张拉的钢丝由松弛引起的应力损失公式为
2.6.5 混凝土收缩和徐变引起的损失
根据《公预规》6.2.7条规定,由混凝土收缩和徐变引起的应力损失可按下式计算
式中:
——全部钢束重心处由混凝土收缩、徐变引起的预应力损失;
——钢束锚固时,全部钢束重心处由预加应力(扣除相应阶段的应力损失) 产生的混凝土法向应力,并根据张拉受力情况,应考虑主梁重力影响;
——配筋率,
——本设计为钢束锚固时相应得净截面面积An
——本设计即为钢束群重心至截面净轴得距离en
——截面回转半径,本设计为
——加载龄期为t0、计算龄期为t时得混凝土徐变系数;
——加载龄期为t0、计算龄期为t时收缩应变。
(1)徐变系数终极值
和收缩应变终极值
的计算
构件理论厚度得计算公式为:
式中:A——主梁混凝土截面面积;
u——与大气接触得截面周边长度。
本设计考虑混凝土收缩和徐变大部分在成桥之前完成,A和u均采用预制梁得数据。对于混凝土毛界面,四分点与跨中截面上述数据完全相同,即:
A=6528cm2
故:
=16.6(cm)
设混凝土和徐变在野外一般条件(相对湿度为75%)下完成,受荷时混凝土加载龄期为20d。
按照上述条件,查《公预规》表6.2.7得到
=2.2,
=0.23×10-3
(2)计算
混凝土收缩和徐变引起得应力损失列表计算在表19内。
表19 预加力作用效应计算表
截
面
钢
束
号
预加应力阶段由张拉束产生的预加力作用效应
siana
cosa
×ΔAp
(0.1KN)
Np0=
×
ΔAp×cosa
(KN)
(表17)
Vp0=
×
ΔAp×sina
(kN)
Mp0
(kN•m)
(表17)
四
分
点
1
0
1
882.5
0
2
0
1
989.5
0
3
0
1
910.3
0
4
0
1
922.3
0
5
0
1
943.0
0
6
0
1
956.5
0
7
0
1
975.4
0
8
0
1
987.8
0
9
0.04785
0.99865
997.9
22.4
10
0.04849
0.99882
1013.8
23.8
11
0.06352
0.99798
1038.8
32.7
12
0.07536
0.99716
1057.1
39.2
13
0.08498
0.99638
1071.7
45.6
Σ
0.32
12.99
5944.5
196.3
6545.6
跨中
Σ
5731.3
0
6873.7
变化点
Σ
6437.1
685.9
3021.4
支点
Σ
6615.7
795
1181.6
表20 各控制点使用阶段消失的预加内力
截
面
钢
束
号
使用阶段消失的预加内力
Np0=
Vp0=
(kN)
Mp0
(kN•m)
四
分
点
1-13
54+213=267
Σ
1378.6
376
1378.6
跨中
Σ
1283.4
0
1369.2
变化点
Σ
1154.9
120.8
631.5
支点
Σ
942.5
135.1
314.3
2.6.6 预加内力计算即钢束预应力损失汇总
施工阶段传力锚固应力
及其产生的预加力:
1.
2.由
产生的预加力
纵向力:
弯矩:
剪力:
式中:
——钢束弯起后与梁轴的夹角,参见表10;
——单根钢束得截面积,
.
可用上述同样的方法计算出使用阶段由张拉钢束产生的预加力Np,Vp,Mp,下面将计算结果一并列入表21内。表22示出了各控制截面得钢束预应力损失。
表21 钢束预应力损失一览表
截面
钢
束
号
预加应力阶段
正常使用阶段
锚固前预应力损失
锚固钢束应力
锚固后预应力损失
钢束有效应力
(MPa)
(MPa)
跨中
1
114.7
53.79
176.4
855.1
54+194=248
607.1
2
114.7
53.79
159.8
871.7
623.7
3
114.6
53.84
138.5
882.4
634.4
4
114.6
53.84
124.4
907..2
659.2
5
114.6
53.93
106.1
925.6
677.4
6
114.6
53.93
91.3
940.2
692.2
7
114.3
53.73
74.6
957.0
709.0
8
114.3
53.73
62.5
969.5
721.5
9
134.8
53.92
53.4
957.8
709.8
10
134.8
53.65
36.4
974.7
726.7
11
134.7
53.71
21.6
989.7
741.7
12
134.5
53.77
12.5
998.7
750.7
13
134.4
53.82
0
1011.4
763.4
四
分
点
1
100.08
53.79
174.1
872.03
54+216=267
605
2
100.08
53.79
158.5
887.63
620.6
3
99.96
53.84
136.7
909.5
642.5
4
99.96
53.84
122.4
923.8
656.8
5
99.96
53.93
103.1
943.01
677
6
99.96
53.93
89.6
956.51
690.5
7
98.28
53.73
72.6
975.39
708.4
8
98.28
53.73
60.2
987.79
720.8
9
97.08
53.92
51.1
997.9
730.9
10
98.28
53.65
34.2
1013.87
746.9
11
88.20
53.71
19.3
1038.79
771.8
12
81.24
53.77
7.8
1057.19
790.2
13
74.52
53.82
0
1071.66
804.7
变化点
1
64.5
53.79
85.2
996.5
54+172=226
770.5
2
64.5
53.79
79.4
1002.3
776.3
3
64.2
53.84
67.2
1014.8
788.8
4
64.2
53.84
57.7
1025.2
799.2
5
64.1
53.93
46.7
1036.7
810.7
6
64.1
53.93
37.4
1045.4
819.4
7
61.5
53.73
30.4
1052.6
826.6
8
61.5
53.73
24.7
1058.7
832.7
9
57.4
53.92
19.0
1067.5
841.5
10
51.3
53.65
14.5
1076.0
850.0
11
45.7
53.71
7.6
1088.6
862.6
12
38.2
53.77
4.1
1099.5
873.5
13
26.4
53.82
0
1114.6
888.6
支点
1
10.5
53.79
43.6
1092.1
54+148=202
890.1
2
10.5
53.79
35.2
1100.6
898.6
3
8.9
53.84
34.1
1103.2
902.2
4
8.9
53.84
28.4
1109.1
907.2
5
8.1
53.93
23.7
1114.6
912.6
6
8.1
53.93
19.6
1118.5
916.5
7
7.5
53.73
15.6
1123.0
921.0
8
7.5
53.73
12.8
1126.3
924.3
9
5.1
53.92
9.4
1131.0
929.0
10
4.2
53.65
7.4
1133.1
931.1
11
3.5
53.71
4.2
1137.5
935.5
12
2.8
53.77
3.9
1138.2
936.2
13
2.1
53.82
0
1142.0
940.0
2.7 主梁截面承载力与应力验算
预应力混凝土梁从预加力开始到受荷破坏,需经受预应力、使用荷载作用、裂缝出现和破坏等四个受力阶段,为保证主梁受力可靠并予以控制,应对控制截面进行各个阶段的验算。在以下内容中,先进行持久状态承载能力极限状态承载能力验算,再分别验算持久状态抗裂验算和应力验算,最后进行短暂状态构件的截面应力验算。对于抗裂验算,《公预规》根据公路简支梁标准设计的经验,对于全预应力梁在使用阶段短期效应组合作用下,只要截面不出现拉应力就可满足。
2.7.1 持久状况承载能力极限状态承载力验算
图13 正截面承载能力计算图
在承载能力极限状态下,预应力混凝土沿正截面和斜截面都有可能破坏,下面验算这两类截面的承载力。
2.7.1.1 正截面强度验算
图13示出正截面承载力计算图示。
(1) 确定混凝土受压区高度
根据《公预规》5.3.2条规定,对于带承托翼缘板的T形截面:当
成立时,中性轴在翼缘板内,否则在腹板内。本设计的 这一判别式:
左边=
=128×43.71×1.3 =7840.7(kN)
右边=
=
考虑三角承托的影响,可近似看成第一类截面计算。
设中性轴到截面上缘的距离为x,则:
求得X=69.8cm
要求
式中:
—预应力受压区高度界限系数,按《公预规》表5.2.1采用,对于C50混凝土,
=0.4;
h0—梁的有效高度
说明该截面破坏时属于塑性破坏状态。
(2)验算正截面承载力
由《公预规》5.2.2条,正截面承载力按下式计算:
式中:
———桥梁结构的重要性系数,按《公预规》5.1.5条取用,本设计按公路II级公路设计 ,故取 1.25.
则上式为:
右边=129224(kN·m)
>
=11756(kN·m)(跨中)
主梁跨中正截面承载力满足要求。其它截面均可用同样方法验算。
2.7.1.2 斜截面强度验算
(1)斜截面抗剪承载力验算
根据《公预规》5.2.6条,计算受弯构件斜截面抗剪承载力时,其计算位置应按下列规定采用:
①距支座中心h/2处截面;
②受拉区弯起钢筋弯起点处截面;
③锚于受拉区的纵向钢筋开始不受力处的截面;
④箍筋数量或间距改变处的截面;
⑤构件腹板宽度变化处的截面。
本设计以变化点为例进行斜截面抗剪承载力验算
复核主梁截面尺寸
T形截面梁当进行斜截面抗剪承载力计算时,其截面尺寸应符合《公预规》5.2.9条规定,即
式中:
——经内力组合后支点截面上最大剪力(kN),各梁最大的Vd为989.8 kN;
——支点截面的腹板厚度(mm),即b=360mm;
——支点截面的有效高度(mm),即
——混凝土强度等级(MPa).
上式=
=
所以本设计主梁的T形截面尺寸符合要求。
截面抗剪承载力验算
验算是否需要进行斜截面抗剪承载力计算。
根据《公预规》5.2.10条规定,若符合下列公式要求时,则不需进行斜截面抗剪承载力计算。
式中:
———混凝土抗拉设计强度(MPa);
———预应力提高系数,对预应力混凝土受弯构件,取1.25.
对于变化点截面:
,
,
所以本设计需进行斜截面抗剪承载力计算。
①计算斜截面水平投影长度
按《公预规》5.2.8条,计算斜截面水平投影长度
:
式中:
——斜截面受压端正截面处的广义剪跨比,
,
当m<1.7时,取m=1.7;
——斜截面受压端正截面内由使用荷载产生的最大剪力组合设计值;
——相应于上述最大剪力时的弯矩组合设计值;
——通过斜截面受压区顶端正截面上的有效高度,自受拉纵向主钢筋的合力点至受压边缘的距离。
计算得
,
对应
得
m=1.31取
②箍筋计算
本设计选用Ф8@20cm的双支箍筋,则箍筋总截面积为:
箍筋间距
,箍筋抗拉设计强度
,箍筋配筋率
为:
③抗剪承载力计算
根据《公预规》5.2.7条规定,主梁斜截面抗剪承载力应按下式计算:
式中:
———斜截面受压端正截面内最大剪力组合设计值,为989.8kN;
———斜截面内混凝土与箍筋共同的抗剪承载力(kK),按下式计算:
——弯起钢筋得抗剪能力
———预应力弯起钢筋得抗拉设计强度取 1280MPa
———预应力弯起钢筋得界面面积
表明上述箍筋的配置是合理的。
(2)斜截面抗弯承载力验算
本设计中,由于梁内预应力钢束数量沿梁跨没有变化,可不必进行强度验算
2.7.2 持久状况构件的应力验算
按持久状况设计的预应力混凝土受弯构件,应计算其使用阶段正截面混凝土的法向压应力,受拉区钢筋的拉应力和斜截面混凝土的主压应力,并不得超过规范规定的限值。计算时荷载取其标准值,汽车荷载应考虑冲击系数。
2.7.2.1 正截面混凝土压应力验算
根据《公预规》7.1.5条,使用阶段正截面应力应符合下列要求:
式中:
———在作用标准效应组合下混凝土的法向压应力,按下式计算:
———由预应力产生的混凝土法向拉应力,按下式计算:
———标准效应组合的弯矩值
表28示出了正截面混凝土压应力验算的计算过程和结果,最大压应力在锚固点下缘,为
,可见其结果符合规范要求。
表22
计算表
截面
应力部位
a-a
b-b
跨中
Np(0.1kN)
33212
33121
Mp(N·m)
4199260
4199260
An(cm2)
6528
6528
Mg1(N·m)
3345857
3345857
Np/An(MPa)
5.4
5.4
Mpyni/In(MPa)
7.4
-12.1
Mg1yni/In(MPa)
-9.3
15.2
(Ms- Mg1)yoi/Io
7.78
-10.09
11.4
-2.5
四分点
5.46
-
N7锚固点
1.26
-
支点
1.58
-
表23
计算表
项
目
荷 载
V
In
Io
腹板
宽 b
上梗肋
a-a
净 轴
n-n
换 轴
o-o
下梗肋
b-b
Sa-n
Sa-o
a
Sn-n
Sn-o
n
So-n
So-o
o
Sb-n
Sb-o
b
0.1KN
cm
跨中
一期恒载
(1)
0
48526885
50135763
16
210847
0.00
260029
0.00
259946
0.00
237024
0.00
短期组合
(2)
735
219857
0.3020
275316
0.3782
275399
0.3783
252914
0.3474
预加力
(3)
0
210847
0.00
260029
0.00
259946
0.00
237024
0.00
短期组合剪力
(4)=(1)+(2)-(3)
0.3020
0.3782
0.3783
0.3474
四分点
短期组合剪力
1.07
1.21
1.21
0.87
N7锚固点
短期组合剪力
0.04
-0.026
-0.024
支点
短期组合剪力
-0.01
-0.107
-0.104
表24
计算表
截面
主应力部位
(MPa)
(MPa)
(MPa)
标准组合
标准组合
标准组合
(1)
(3)
(5)
跨中
a-a
4.3
0.3020
-0.009
o-o
6.1
0.3782
-0.010
n-n
6.2
0.3783
-0.010
b-b
7.0
0.3474
-0.005
四分点
a-a
4.1
1.07
-0.0202
o-o
4.6
1.21
-0.174
n-n
5.3
1.21
-0.170
b-b
5.4
0.87
-0.058
N7锚固点
a-a
1.26
0.04
-0.001
o-o
4.25
-0.026
-1.35×10-4
n-n
4.5
-0.024
-1.50×10-4
支点
a-a
1.58
-0.01
-6.33×10-5
o-o
4.33
-0.107
-2.50×10-3
n-n
4.58
-0.104
-2.50×10-3
注:在混凝土主应力计算中,习惯上在计算剪力时取用各计算截面的最大剪力,计算法向应力时取用各计算截面的最大弯矩,实际上,由于对同一计算结面不可能同时出现最大剪力和弯矩,因此上表所计算的主应力值稍偏大。
表25 正截面混凝土压应力验算表
应力部位
跨中上缘
跨中下缘
四分点上缘
四分点下缘
变化点上缘
变化点下缘
支点上缘
支点下缘
Np(0.1kN)
33212
33212
32586
32586
32158
32158
32146
32146
Mp(N·m)
4199260
4199260
3865475
3865475
2798532
2798532
1689546
1689546
An(cm2)
6528
6528
6528
6528
6985
6985
9637
9637
Wn
448374
275927
451975
279736
471602
357287
537362
390306
Wo
477695
339850
474022
335129
471677
378258
536577
399148
Np/An
5.1
5.1
5.0
5.0
4.6
4.6
3.3
3.3
Mp/Wn
-9.4
15.2
-8.6
13.8
-5.9
7.8
-3.1
5.1
-4.3
20.3
-3.6
18.8
-1.3
12.4
0.2
8.4
Mg1/Wn
6.5
-10.5
5.4
-7.8
0.8
-1.1
0
0
(Mk-Mg1)/Wo
7.1
-5.7
5.2
-3.7
0.9
0.5
0
0
13.6
-16.2
10.6
-11.5
1.7
-0.6
0
0
9.3
4.1
16
7.3
0.4
11.8
0.2
8.4
注:计算上缘最大压应力时,Mk为荷载标准值的最大弯矩组合,见表7;计算下缘最大应力时,Mk为最小弯矩组合,即活载效应为0。
·2.7.2.2预应力筋拉应力验算
根据《公预规》7.1.5条,使用阶段预应力筋拉应力应符合下列要求:
式中:
———预应力筋扣除全部预应力损失后的有效预应力;
———在作用标准效应组合下受拉区预应力筋产生的拉应力,按下式计算:
,
———分别为钢束重心到截面净轴和换轴的距离,即
,
———在作用标准效应组合下预应力筋重心处混凝土的法向拉应力;
———预应力筋与混凝土的弹性模量比。
取最不利的外层钢筋N2进行验算,表示出了N2号预应力筋拉应力的计算过程和结果,最大拉应力在跨中截面,为1298.84MPa,可见其结果符合规范要求。
2.7.2.3截面混凝土主压应力验算
此项验算主要为了保证混凝土在沿主压应力方向破坏时也具有足够的安全度。以1号梁的跨中截面为例,对其上肋(a-a)、和下肋(b-b)等四处分别进行主压应力验算,其它截面均可用同样方法计算。
根据《公预规》7.1.6条,斜截面混凝土主压应力应符合下列要求:
式中:
———由作用标准效应组合
和预应力产生的混凝土主压应力,按下式计算:
式中:
——在计算主应力点,由荷载标准值组合和预应力产生的混凝土法向应力;
——在计算主应力点,由荷载标准值组合和预应力产生的混凝土剪应力。
表30示出了
的计算过程,表示出了
的计算过程,混凝土主压应力计算结果见表32最大主压应力为15.77MPa,可见其结果符合规范要求。
表 26
计算表
截面
应力部位
a-a
b-b
跨中
Np(0.1kN)
33212
33121
Mp(N·m)
4199260
4199260
An(cm2)
6528
6528
Mg1(N·m)
3345857
3345857
Np/An(MPa)
5.0
5.0
Mpyni/In(MPa)
-8.9
17.3
Mg1yni/In(MPa)
5.7
-3.5
(Ms- Mg1)yoi/Io
7.8
-8.4
9.4
10.4
四分点
5.46
14.2
N7锚固点
1.26
-
支点
1.58
-
注:计算a-a,o-o,n-n处压应力时,Mk为荷载标准值的最大弯矩组合,见表7所示;计算b-b处压应力时,Mk为最小弯矩组合,即活载效应为0。
表27
计算表
项
目
荷 载
V
In
Io
腹板
宽 b
上梗肋
a-a
净 轴
n-n
换 轴
o-o
下梗肋
b-b
Sa-n
Sa-o
a
Sn-n
Sn-o
n
So-n
So-o
o
Sb-n
Sb-o
b
0.1KN
cm
跨中
一期恒载
(1)
0
5.2E+07
7.1E+07
20
250005
0.00
293170
0.00
293026
0.00
194587
0.00
短期组合
(2)
1843.7
345415
0.21
383587
0.23
383731
0.23
277450
0.17
预加力
(3)
0
250005
0.00
293170
0.00
293026
0.00
194587
0.00
短期组合剪力
(4)=(1)+(2)-(3)
0.45
0.50
0.50
0.36
四分点
短期组合剪力
1.37
1.54
1.54
1.11
N7锚固点
短期组合剪力
0.16
0.14
0.14
支点
短期组合剪力
0.11
0.06
0.06
表28
计算表
截面
主应力部位
(MPa)
(MPa)
(MPa)
标准组合
标准组合
标准组合
(1)
(3)
(5)
跨中
a-a
9.11
0.45
9.13
o-o
8.65
0.5
8.68
n-n
8.62
0.5
8.65
b-b
13.73
0.36
13.7
四分点
a-a
6.45
1.37
6.73
o-o
8.26
1.54
8.54
n-n
8.38
1.54
8.65
b-b
15.69
1.11
15.8
N10锚固点
a-a
1.42
0.16
1.44
o-o
4.25
0.14
4.25
n-n
4.48
0.14
4.48
支点
a-a
1.58
0.11
1.59
o-o
4.33
0.06
4.33
n-n
4.58
0.06
4.58
注:在混凝土主应力计算中,习惯上在计算剪力时取用各计算截面的最大剪力,计算法向应力时取用各计算截面的最大弯矩,实际上,由于对同一计算结面不可能同时出现最大剪力和弯矩,因此上表所计算的主应力值稍偏大。
2.7.3 短暂状况构件的应力验算
桥梁构件的短暂状况,应计算其在制作,运输及安装等施工阶段混凝土截面边缘的法向应力.
·2.7.3.1预加应力阶段的应力验算
此阶段指初始预加力与主梁自重力共同作用的阶段,验算混凝土截面下缘的最大压应力和上缘的最大拉应力。
根据《公预规》7.2.8条,施工阶段正截面应力应符合下列要求:
式中:
,
———预加应力阶段混凝土的法向压应力、拉应力、按下式计算:
,
———与构件制作、运输、安装各施工阶段混凝土立方体抗压强度
相应的抗压强度、抗拉强度标准值,本设计考虑混凝土强度达到C45时开始张拉预应力钢束,则:
,
。
表28示出了预加应力阶段混凝土法向应力的计算过程。
2.7.3.2吊装应力验算
本设计采用两点吊装,吊点设在两支点内移59cm处。即两吊点的距离小于主梁得计算跨径故可不用验算
2.8 主梁端部的局部承压验算
后张法预应力混凝土梁的端部,由于锚头集中力的作用,锚下混凝土将承载很大的局部压力,可能使梁端产生纵向裂缝,需进行局部承压验算。
如图18a所示,在锚固端设置两块厚20mm的钢垫板,即在N11~N13的3根钢束锚下设置200×712mm的垫板,在1N1~N10的六根钢束锚下设置350×1166mm的垫板2。在钢垫板下等于梁高(230mm)的范围内并且布置21层φ8的间接钢筋网,钢筋网的间距为10cm,其中锚下第一层钢筋网的布置见图14b所示。根据锚下钢垫板的布置情况,以下分上、下两部分各自验算混凝土局部承压强度。
a. 锚下钢垫板布置 b. 锚下间接钢筋网
图14 锚下钢垫板的布置情况
按《桥规》第5.1.16条和第4.1.24条规定,预应力混凝土梁局部承压强度按下列公式计算:
式中:
——局部承压时的纵向力。在梁端两块钢垫板中,分别考虑除最后张拉的一束为控制应力外其余各束均匀为传力锚固应力,可计算出垫板1、2的
各为
和
;
——混凝土局部承压强度的提高系数,按下式计算:
——局部承压时的计算底面积(扣除孔道面积);
——局部承压(扣孔道)面积;
——配置间接钢筋时局部承压强度提高系数,按下式计算:
——包罗在钢筋网配筋范围内的混凝土核心面积;
——混凝土抗压设计强度,对于40号混凝土
。本示例考虑在主梁混凝土达到
强度时开始张拉钢束,所以
;
——间接钢筋抗拉设计强度,对于Ⅰ级钢筋Rg =24MPa;
——间接钢筋的体积配筋率,对于方格钢筋网
、
和
、
——钢筋网分别沿纵、横方向的钢筋根数及单概念钢筋的截面面积;
——钢筋网的间距。
对于钢垫板1(见图18a):
∴ 强度提高系数为
间接钢筋体积配筋率
把计算数值代入上述公式,则
公式右边=0.6×(1.6×21.7+2×0.01065×1.442×240)×11365×10-1=3495KN
∴
对于钢垫板2:
∴
(符合要求)
注:在垫板1和2的局部承压强度计算中,上述强度计算公式等号右边由第二项算得的数值均未超过第一项的50%。
梁端局部承压区的抗裂计算
按《桥规》第5.1.25条规定,计算公式为:
式中:
——考虑局部承压时的纵向力(KN),数值与前节计算的相同;
——系数,按下式计算:
——与垫板形式及构件相对尺寸有关的系数,对于本例的方型垫板V=2;
——局部承压板垂直于计算截面(受剪面)方向的边长与间接配筋深度(本例为
)之比;
——梁端部区段沿荷载轴线切割的计算截面积(其高度等于间接配筋深度),其中应扣除孔道沿荷载轴线的截面面积(cm2);
——混凝土抗拉设计强度(MPa),考虑40号混凝土达90%强度时张拉钢束,则
.
对于钢垫板1:
∴
鉴于沿截面A的深度方向布置21层间接钢筋网,并且每层有2根钢筋通过截面A,则
代入计算公式:
∴
(符合要求)
对于钢垫板2:
A=36×230-2×5×230=5980cm2
Ag=21.126cm2
至此,便完全说明了在主梁混凝土达到90%强度时可以张拉预应力钢束。
2.9主梁变形验算
为了掌握主梁在各受力阶段的变形(通常指竖向挠度)情况,要求计算各阶段的挠度值,并且对体现结构刚度的活载挠度进行验算。本例在计算中,以四分点截面为平均值将全梁近似处理为等截面杆件,然后按材料力学方法计算1号梁跨中挠度。
2.9.1 计算由预加应力引起的跨中反拱度
计算公式:
式中:
——由初始张拉力Pi作用下的跨中短期挠度;
——张拉锚固时各根钢束的预加弯矩;
——单位力作用在跨中时所产生的弯矩。
图15示出了反拱度的计算图式,其中Myo图绘在b图内(只示出左半部分)。设Myo图的面积及其形心至跨中的跨离分别为A和d,并将它划分成四个规则图形,分块面积及形心位置为Ai和di,计算公式均列入表29内。
上述积分按图乘法计算,即单束反拱度。
图15 反拱度计算图
表29 分块面积及形心位置为Ai和di计算公式
分 块
面积Ai
(cm2)
形心位置di
(cm)
形心处的
值
(cm2)
矩 形1
矩 形2
三角形
弓形
半个Myo图
表中:
为锚固点截面的钢束重心到净轴的竖直距离
为钢束起弯点至净轴的竖直距离,
为钢束弯起角。
跨中反拱度
根据《公预规》6.5.4条,考虑长期效应的影响,预应力引起的反拱值应乘以长期增长系数2.0,即:
2.9.2 计算由荷载引起的跨中挠度
根据《公预规》6.5.2条,全预应力混凝土构件的刚度采用
,则恒载效应产生的跨中挠度可近似按下列公式计算:
EMBED Equation.DSMT4
短期何在效应组合产生的跨中挠度可近似按下列公式计算:
EMBED Equation.DSMT4
表30 各束引起的反拱度fi计算表
计 算 数 据
yjx=138.00cm Ij =50135763cm4 Ek =3.3×104MPa
分块
单位 束号
项目
N1
N2
N3
N4
N5
N6
N7
N8
N9
N10
N11
N12
N13
矩
形
1
A1·d1
=
·A1
cm3
30108842
37426395
31455060
20613759
27659852
21313755
10685218
3261948
28145
矩
形
2
A2·d2
=
·A2
cm3
219468729
160077905
101157447
23672285
15322956
24368578
-25245921
-73729138
-12177783
三
角
形
A3·d3
cm3
6755000
22116591
41710485
89806425
65422364
96358745
100982124
108333360
110996034
弓
形
A4·d4
cm3
2311902
7869366
15587936
36771560
28574635
40235654
43529010
49797786
55379565
Myo
图
A
cm
263739
238363
208561
209362
210265
215896
175075
138920
100.894
D
0.1KN
980.68
954.39
910.58
816.12
786.35
762.65
742.25
631.04
442.37
cm
2499.185
510.355
530.285
582.205
595.21
609.23
616.935
670.335
762.495
Myo
KN
425
432
442
449
458
464
472
481
483
487
491
492
502
0.853
0.869
0.821
0.834
0.772
0.784
0.877
0.852
0.821
0.816
0.809
0.797
0.700
根据《公预规》6.5.3条,受弯构件在使用阶段的挠度应考虑何在长期效应的影响,即按荷载短期效应组合计算的挠度值,乘以挠度长期增长系数
,对C50混凝土,
,则荷载短期效应组合引起的长期挠度值为:
EMBED Equation.DSMT4
恒载引起的长期挠度值:
EMBED Equation.DSMT4
2.9.3 结构刚度验算
按《公预规》6.5.3条规定,预应力混凝土受弯构件计算的长期挠度值,在消除结构自重产生的长期挠度后梁的最大挠度不应超过计算结构的1/600,即:
可见,结构刚度满足规范要求。
2.9.4 预拱度的设置
按《公预规》6.5.3条规定,当预加力产生的长期反拱值大于荷载短期效应组合计算的长期挠度时,可不设预拱度。本设计中预加力产生的长期反拱值为 21cm,大于按荷载短期效应组合计算的长期挠度值 16.8 cm,满足规范要求可不设预拱度。
第3章 横隔梁计算
3.1 确定作用在跨中横隔梁的可变作用
鉴于具有多根内横隔梁的桥梁跨中处的横隔梁受力最大,通常只计算跨中横隔梁的作用效应,其余横隔梁可依据跨中横隔梁偏安全的选用相同的截面尺寸和配筋。
根据《桥规》4.3.1条规定,桥梁结构的局部加载计算应采用车辆荷载,图16表示出跨中横隔梁纵向的最不利荷载布置。
图16 跨中横隔梁的受载图式(尺寸单位:mm)
纵向—行车轮和人群荷载对跨中横隔梁的计算荷载为:
汽车:
跨中横隔梁受力影响线的面积:
人群荷载:
3.2 跨中横隔梁的作用效应影响线
通常横隔梁的弯矩为靠近桥中线的截面较大,而剪力则靠近两侧边缘处的截面较大,如图22跨中横隔梁,本设计只取A、B两个截面计算横隔梁的弯矩,取1号右梁和2号梁右截面计算剪力,本设计采用刚性横梁法计算横隔梁作用效应,先需作出相应的相应影响线。
3.2.1 绘制弯矩影响线
3.2.1.1 计算公式
如图22所示,在桥梁跨中当单位荷载P=1作用在j号梁轴上时,i号梁受的作用为竖向力ηij。因此,由平衡条件就可写出A截面的弯矩计算公式:
当P=1作用在截面A的左侧时:
即:
式中:
——
号梁轴A截面的距离;
——单位荷载
作用位置到A截面的距离。
当P=1作用在截面A的右侧时,同理可得:
3.2.1.2 计算
值
按照姚玲主编《桥梁工程》的式(2-6-33)、(2-5-34)和式(2-5-35)可以推导求得:
式中:
——分别为i梁的抗弯惯矩和抗扭惯矩;
——单位荷载
作用位置到横截面中心的距离,当
在中心之左时取正值,在中心之右时取负值。其它符号均同本例第二节中说明。
对于本例各主梁截面相同,并取
,则上式为:
当p=1作用在1号梁轴上时,
,同时
(见表4)
EMBED Equation.3
当p=1作用在5号梁轴上时,
,则
当p=1作用在2号梁轴上时,
,则
同理
计算弯矩影响线坐标值
对于A截面的弯矩MA影响线可计算如下:
作用在1号梁轴上时:
作用在5号梁轴上时:
作用在4号梁轴上时:
以上述三点坐标和A截面的位置,便可绘出MA影响线。
同理,MB影响线计算如下
绘出
影响线
3.2.2 绘制剪力影响线
(1)对于1号主梁右截面的剪力
影响线可计算如下:
作用在计算截面以右时:
作用在计算截面以左时:
绘成的
影响线如图17。
(2)对于2号主梁右截面的剪力
右影响线可计算如下:
作用在计算截面以右时:
如
作用在3号梁轴上时:
同理
作用在计算截面以左时:
绘成的
影响线
图17 中横隔梁内力影响线图
3.3 截面作用效应计算
计算公式:
截面内力
式中:
——横隔梁冲击系数,对于它的计算,《桥规》中无明确规定,本例近拟地取用主梁的冲击系数;
——车道折减系数,对于双车道不折减,即
;
——车辆对于跨中横隔梁的计算荷载,包括
和Pog;
——与计算荷载Po相应的横隔梁内力影响线的竖坐标值。
计算荷载Poq和Pog在相应影响线上的最不利位置加载见图17所示,截面内力的计算均列入表内。
截面配筋计算
图18和图19分别表示横隔梁正弯矩配筋(4φ18布置在下缘)和负弯矩配筋(2φ18布置在上缘),并且示出配筋计算的相应截面。剪力钢筋选用间距Sk为20cm的2φ8双肢筋筋。经过横隔梁正截面和斜截面强度的验算,上述配筋均能满足规范的有关规定。由于这部分的计算内容与主梁截面强度验算雷同,故从略。
表31 横隔梁截面作用效应计算表
汽车Po(kN)
124.922
人群qo(kN/m)
19.5
MA(kN·m)
0.922
0.2876
MA
462
MB(kN·m)
0.9658
0.1760
MB汽
-51
MB人
MB人=(-1.2443+0.8468)×19.5×1.15=-46 (kN·m)
(kN)
0.5264
0.3306
0.1782
0.0067
237
=0.5×(0.4514+0.4452) ×0.15×19.5=1.3(kN)
(kN)
0.6841
0.3543
0.2074
-0.1223
299
控制内力
MAmax(kN·m)
0+1.4×462=646.8
MBmin(kN·m)
0-1.4×97=-135.8
V(kN)
0+1.4×299 =418
3.4 截面配筋计算
图18和图19分别表示横隔梁正弯矩配筋(4Φ20布置在下缘)和负弯矩配筋(2Φ20布置在上缘),并且示出配筋几的相应截面。剪力钢筋选用间距为Sk=200mm的2φ8双肢箍筋。经过横隔梁正截面和斜截面承载力的验算,上述配筋均能满足规范的有关规定。由于这部分的计算与主梁截面承载力的验算雷同,故从略。
图18 正弯矩配筋及其计算截图 图19 负弯矩配筋及其计算截图
(尺寸单位:cm) (尺寸单位:cm)
第4章 行车道板计算
考虑到主梁翼缘板内钢筋是连续的,故行车道板可按悬臂板(边梁)和两端固结的连续板(中梁)两种情况来计算。
4.1 悬臂板荷载效应计算
由于宽跨比大于2,故按单向板计算,悬臂长度为0.72m,中间铰接.
4.1.1 永久作用
主梁架设完毕时桥面板可看成72cm长的单向悬臂板,计算图式见图20
图20 悬臂板计算图式(尺寸单位:mm)
计算弯矩根部永久作用效应
4.1.2 活载内力
计算如图 取P=140kn,
由图得
(1)车轮在板的跨径中部时
垂直于板的跨径方向的荷载分布宽度:
,取a=1.06m,
(2)车轮在板的支承处时
垂直于板的跨径方向荷载的有效分布宽度:
车轮在板的支承附近,距支点距离为x时
垂直于板的跨径方向荷载的有效分布宽度:
4.2 荷载效应组合
将加重车后轮作用于板的中央,求得简支板跨中最大可变作用(汽车)的弯矩为:
EMBED Equation.DSMT4 =25.3(kN·m)
计算支点剪力时,可变作用必须尽量靠近梁肋边缘布置。考虑了相应的有效工作宽度后,每米板宽承受的分布荷载:
综上所述,可得到连续板可变作用(汽车)效应如下:
支点断面弯矩:
支点断面剪力:
跨中断面弯矩:
。
作用效应组合
按《桥规》4.1.6条进行承载能力极限状态作用效应基本组合。
支点断面弯矩:
支点断面剪力:
跨中断面弯矩:
4.3 截面设计、配筋与承载力验算
悬臂板及连续板支点采用相同的抗弯钢筋,故只需按其中最不利荷载效应配筋,即Md=-27 kN·m。其高度h=22cm,净保护层a=3cm。若选用
12钢筋,则有高度ho为:
按《公预规》5.2.2条:
验算
按《公预规》5.2.2条:
查有关板宽1m内钢筋截面与距离表,当选用
12钢筋时,需要钢筋间距为12cm,此时所提供的钢筋面积为:As=9.42>9.34cm2。由于此处钢筋保护层于4试算值相同,实际配筋面积又大于计算面积,则其承载能力肯定大于作用效应,故承载能力验算可从略。
连续板跨中截面处的抗弯钢筋计算同上,此处从略。计算结果需在板的下缘配置钢筋间距为12cm的
12钢筋。为使施工简便,取板上下缘配筋相同,均为
12@120mm。配筋布置如图22。
按《公预规》5.2.9条规定,矩形截面受弯构件的截面尺寸应符合下列要求。即:
满足抗剪最小尺寸要求。
按《公预规》5.2.10条,
即:
时,不需要进行斜截面抗剪强度计算,仅按构造要求配置钢筋。
根据《公预规》9.2.5条规板内应设置垂直于主钢筋的分布钢筋,直径不应小于8cm,间距不应大于200mm,因此本例中板内分布附近用
8@200mm。
结束语
两个多月过去了,我的毕业设计也在今天完工。毕业设计是我们在校期间最后一个重要的课程。通过毕业设计我受到了本专业系统、综合的训练和实战演练,提高了自己综合运用所学知识能力和实践技能的能力,同时也培养了我的创新能力。因此,通过此次毕业设计,我掌握了T型梁桥设计的内容、步骤和方法以及计算过程。锻炼了自己对基本技能的运用,加强了自己解决疑难问题的能力,提高了对计算机应用的技能,特别是对CAD的熟练操作;还培养了自己正确、熟练运用规范、手册及参考书的能力。
我做的是T型梁桥设计,涉及到的内容就比较多。但是遇见问题最多还是主梁截面特性和各截面的应力计算上,这部分涉及到的知识点和公式很多,要考虑的因素也很多,是专业知识的一个很全面的贯通,做好这部分得查阅很多相关的资料。还得感谢李清富老师的细心指点让我有了头绪。
整个设计下来,总结了一些设计过程中应该注意的问题:
(1)在动手设计之前,先了解本次设计内容、查阅相关参考资料是十分必要的,在了解基本要求后认真熟悉规范的规定更是关键所在;另外,还应该认真的学习院系下发的关于毕业设计的每个文件,严格按要求进行设计;
(2)在动手设计后,应根据任务要求合理安排和及时、灵活的调整进度;
(3)不要害怕设计会犯错误,而是要勇于面对任何的错误和挫折,不断地总结和积累经验;勇于挑战自我,敢于超越设计进度安排,这对于自己思维锻炼有很大的作用。
(4)积极查阅各种参考资料,主动向指导老师请教,热心与同学讨论交流,团结协作,这都对设计有着很大帮助。
参考文献
[1] 刘龄嘉,桥梁工程[M],北京,人民交通出版社,2007.1
[2] 叶见曙,结构设计原理[M],北京,人民交通出版社,2005.6
[3] JTGD60-2004,公路桥梁设计通用规范[S]
[4] JTGD62-2004,公路钢筋混凝土及预应力混凝土桥涵设计规范[S]
[5] 河海大学、大连理工大学、西安理工大学、清华大学合编,水工钢筋混凝土结构学[M],北京,中国水利水电出版社,1996.10
[6] 徐光辉、胡明义,公路桥涵设计手册梁桥(上册)[M],北京,人民交通出版社,1996
[7] 龙驭球、包世华,结构力学教程(Ⅰ)[M],北京,高等教育出版社,2000.7
[8] Gotthard Franz, Konstruktionslehre des Stahlbeton[R],Berlin,
Springer-Verlag, 1964
[9] 孙训方、方孝淑、关来泰,材料力学[M],北京,高等教育出版社,1994.9[10]高岛春生,道路桥的横分配实用计算法(前编)[M],东京,现代社,1968[11]Poh K W, Attand M M, Calculating the load-deflection behaviour of simply-supported composite slabs with interface slip[J],Engineering structure, 1993.15
致 谢
在这份毕业设计即将脱稿之际,我向所有在这期间关心和帮助我的老师、同学和朋友们致以衷心的感谢!
首先向我的指导老师李清富教授表示最真诚的感谢和敬意!老师治学严谨,学识渊博,品德高尚,平易近人,无论是在理论学习阶段,还是在论文的选题、资料查询、开题、研究和撰写的每一个环节,无不得到老师的悉心指导和帮助,他在我学习期间不仅传授了做学问的秘诀,还传授了做人的准则,这些都将使我终生受益。借此机会向老师表示衷心的感谢!
我还要感谢我们设计小组的成员,在我的设计过程中给予的大量无私帮助,在设计过程中他们的陪伴、鼓励让我能安心投入设计,遇到问题时他们提议、援助使我的设计能够顺利的进行。
最后,我要感谢我的母校,是她教育和培养了我。此次毕业设计或许是我四年大学生活中短时间受益最深的环节。通过本次设计,我对桥梁工程设计的步骤有了一个初步的认识,在理论及实践上均上了一个新台阶,更重要的是使我对自己在处理各方面问题时有一个较全面的认识,他必将对以后的工作及学习起到积极的作用,使我更加坚定了走向成功的信念,使我在最后告别母校之际充满对未来的信心!
在此,向一直以来辛勤工作的恩师致敬!
张朋杰
二零一一年六月
中英文翻译
英文原著
Ultimate strength of continuous composite box-girder bridges with precast decks
1. Introduction
A prefabricated concrete slab is very attractive both for the new construction and the replacement of deteriorated bridge decks because the system can ensure the quality of concrete decks, improve working environments for the workers, and reduce construction time and traffic disruption. A precast deck bridge has two types of connections, shear connection between steel girder and prefabricated slab and transverse joints between precast panels. Fig.1 shows the overview of a composite bridge with full-depth precast decks dealt with in this paper.
There have been several experiments on composite beams with precast decks. Through observation of the behaviour of shear connections , an empirical equation for shear stiffness of the connection was suggested from the load-slip curves of push-tests. Flexural fatigue tests on a simple span composite beam showed the capacity for shear load redistribution between the studs. From these studies, ultimate strength and fatigue endurance of stud shear connection in precast deck composite bridges were evaluated.
Many serviceability problems, such as cracking and water leakage at transverse joints, have been reported in several bridges. Research on the field performance of precast deck bridges showed that the major problem is cracking at the joints. In this study, the transverse joints of the precast decks had female-to-female joints without reinforcement except that of longitudinal internal tendons. Special care is required in precast decks without reinforcement at the transverse joints and the slabs should be designed to prevent cracking and leakage at the joints under service load. It is therefore necessary to keep the joints compressed during the service life of the bridge in order to prevent cracking and leakage at the joints. For this purpose, a design criterion for crack prevention at the joint without reinforcement should be such that it does not permit tension at the joints to occur under service loads.
Experimental works and analytical studies were performed to investigate cracking behaviour at the transverse joints of a precast deck bridge . From the studies, several design considerations were suggested. Tensile stresses occurring at the joints locally are important to determine the magnitude of the effective prestress. Losses of compressive stress at the top fibre of the joints are considerable and should be evaluated carefully in determining the magnitude of the initial prestress. It is obvious that the losses can be decreased effectively by reducing the concrete shrinkage strain. Prestressed composite bridges could be uneconomical because of considerable prestress losses by long-term behaviour of concrete, so that advantages of precast elements, such as prestressing time after casting precast concrete, should be considered in design.
Numerous experimental works and analyses were performed to establish the design basis for continuous composite bridges with precast decks . In those studies, experiments on continuous composite beams were carried out to investigate the behaviour of continuous beams and to confirm the proposed design criterion for crack prevention at the joints. It is sufficient to prevent tensile stresses at the female -to-female joint in a continuous precast deck bridge.
The bridges which satisfy service limit states, also, should be evaluated for ultimate strengths to define limit states. In order to calculate a flexural resistance of composite section, sectional classes and a degree of shear connection should be evaluated. From previous experimental studies , it was concluded that the ultimate strength of stud shear connectors in precast deck bridges is proportional to the cross-sectional area of the stud shank and decreases with an increase of the bedding layer thickness. In this paper, experimental and analytical studies of two-span continuous composite bridges with open box girder section were conducted. Cracking, yielding and ultimate loads were evaluated and compared with the test results for design of continuous composite bridges with precast decks. To evaluate yielding loads of continuous bridges, an uncracked section method considering moment redistribution which is defined in EUROCODE 4, was considered. In calculation of ultimate strengths, full or partial shear connection and sectional classes which were defined in EUROCODE or AASHTO LRFD Specifications were considered. Also, through numerical analysis considering material nonlinearities, moment–curvature relationship and moment redistributions were estimated.
2. Experimental works
2.1. Specimens
For medium span bridges, composite box girders can be an attractive form of construction.Two different types of box girders may be considered — those where complete closed steel boxes are fabricated, and those where an open ‘U’ section is fabricated. For either class, the box section may be either rectangular or trapezoidal. Prefabricated slabs could be effectively applied to the open-topped steel box girder bridges because form work for casting concrete can be avoided. In this experimental study, a continuous composite box-girder bridge of trapezoidal ‘U’ section with prefabricated slabs was built.
Two continuous composite box-girder bridges with precast decks named CBG1 and CBG2 were fabricated. CBG1 has 10–10 m two span and CBG2 has 20–20 m two span continuous bridges. Two box girder bridges have same sectional dimensions as shown in Fig.2(a). In CBG models, each precast panel has six block-outs for stud shear connectors and five 40 mm ducts for post-tensioning. In order to introduce longitudinal prestress, five tendons of 15.2 mm diameter were installed into the deck and a bolt-type anchorage was adopted. In addition, in CBG2, the composite section in negative moment regions was prestressed by external tendons after shear connection (Fig.2(c)). Stud shear connectors were installed on top flanges of the steel girder to achieve full shear connection. Diaphragms were placed on each support and additional K-type bracings were located between supports.Inside the steel box, longitudinal, horizontal and vertical stiffeners were welded.
In the scope of the section classes proposed by EUROCODE 3 and EUROCODE 4 , the classification of cross-sections in the test models was as follows. The web plate in the negative moment region is Class 1 in according to Eq.(1), and also the lower flange in the negative moment region is Class 1 in accordingto Eq. (2). Also from the viewpoint of AASHTO LRFD specification, the web plate and lower flange in negative moment regions are all compact sections by Eqs.(3) and (4). As a composite box girder section has high torsional stiffness, this is expected to be prevent lateral torsional buckling and show sufficient rotation capacity. Therefore ultimate load may be calculated using the plastic global analysis,and compared with test results.
2.2. Material properties
Material properties of the steel sections, concrete and mortar are listed in Tables 1 and 2, respectively. Five internal tendons were used in CBG models and additionally two external tendons were installed in CBG2. These tendons’areas and properties were the same.
2.3. Procedure and measurements
Two concentrated loads were applied at mid-span of the composite bridge by an MTS closed loop electro-hydraulic testing system as shown in Fig.3. In CBG1, static tests for the observation of the elastic behaviour of the model were performed and then fatigue tests to 1000,000cycles were carried out. After these tests, static tests to investigate after cracking and inelastic behaviour of the composite bridge model were carried out. In CBG2, the first loading was made until a crack occurred in slabs near an interior support and then the last loading was made until large deformation had developed .
Measurement contents of CBG models are shown in Fig.4. Displacements of the continuous bridges were measured at each mid-span with linear variable differential transformers (LVDTs; LV1, LV2). LVDTs were also installed to measure the relative displacement between steel and concrete as presented in Fig.4 (SL1–SL6). Strain distributions of sections A, B and C were observed in concrete slab and steel girder (Fig.4). In CBG2, to find out the prestressing force change, two load cells were installed at the anchorages of external tendons.
3. Experimental results and analysis
3.1. Full or partial shear connection
In the test models, it was intended that shear connections were installed to achieve full shear connections. The ultimate strength of a stud shear connector was determined from Eq.(5) developed by Kim.
To achieve full shear connection,the degree of shear connection,η which is defined as the strength of the shear connection in a shear span,as a proportion of the strength required for full shear connections, should be higher than unity.
In both CBG1 and CBG2, the degree of shear connection was estimated to be higher than unity according to Eq. (6) and then in the tests, maximum slips were measured at 1 mm until ultimate load. From this result, it is considered that the shear connection would not reach the ultimate load state thus the test specimens could develop the full plastic moment of the composite section. Therefore it is concluded that Eqs. (5)and (6) are effective in estimating the ultimate strength of the shear connection and the degree of shear connection.
3.2. Cracking,yielding and ultimate load
Previous research has been focused on the cracking load and post-cracking behaviour to confirm the serviceability in precast deck continuous bridges . In this study, cracking load, yielding load and ultimate load were evaluated and then compared with test results as shown in Table3.
Before the crack had occurred near the interior support, all spans behaved as an uncracked section, and thus the cracking load could be evaluated. In Table 3, test results of the cracking load were higher than calculations because the bond strengths between the transverse deck joints had been neglected [13]. For the estimation of the yielding and ultimate load in maximum negative and positive bending, it is necessary to consider moment redistributions. This is because of the cracking of slabs and the yielding of the girder near the interior support. Due to the cracking and yielding, moment redistribution occurs and the positive moment is increased and negative moment is decreased. In the tests, yielding occurred at almost the same time in maximum positive and negative moment regions.
The yielding load was calculated by the uncracked section method using moment redistribution.After crackingload, about 15% moment redistribution from the negative to the positive moments section produced yielding in the negative moment region and about 40% moment redistribution produced yielding in the positive moment region. According to EUROCODE 4, 40% moment redistribution can be considered at the ultimate states of class 1 sections, but, in plastic states, it is anticipated that more moment redistribution may occur. From Table3 in CBG1, calculations were shown to be similar to the test result. But in the test result, yielding of the positive moment region had occurred earlier than that of the negative moment region. This is considered to be due to residual stress. In CBG2, calculations were somewhat under-estimated because external tendon and anchoragesectionwereneglectedinthe calculationofyieldingload.
The ultimate load was calculated using the concept of a plastic mechanism. Because the section classes of test specimens were all class 1 in positive and negative moment regions, the plastic global analysiscan be used because a sufficient rotationcan be assured. In this evaluation, the effect of the shear was not considered because it was insignificant compared with the bending effect.
Table 4 shows the ratio of the test results and calculations in cracking, yielding and ultimate load. From these results, it can be said that if the composite section is class 1, the uncracked section method in EUROCODE 4 by the 15% moment redistribution after cracking and the 40% moment redistribution in ultimate states could be applied in continuous composite box-girder bridges with precast decks and in this case, the evaluation of the ultimate load by the plastic global analysis can be made efficiently.
3.3. Evaluation of plastic moment
Positive moment regions could be assumed as an uncracked section and negative moment regions could be assumed as a cracked section such as Fig.5. In CBG1,reinforcement and internal tendons were included in calculation of plastic moments of negative moment regions (Fig.5(b)). In CBG2, in addition, the external tendon was also included in calculation of plastic moments as shown in Fig. 5(c). In this case, the plastic moment for the negative moment section could be calculated using the following equation:
Thus,in the evaluation of the ultimate load by the mechanism in Table 3 ,the sectional assumptions and Eq. (7) for plastic moments were used. In CBG1, owing to the lack of capacity of the loading equipment, the maximum observed loading was 1800 kN. From the measured girder strain, the webs of sections A and C (Fig.4) did not yield fully until 1800 kN. In CBG2, though the external tendons did not yield in the test, it was assumed that the axial force of external tendons was yielding force in the plastic analysis. Therefore, the ultimate load calculated by the mechanism was somewhat overestimated. From Table 3,it is considered that the rigid plastic global analysis using the assumption of uncracked and cracked section for the positive and negative moment region respectively, could be applied to precast deck composite box girder bridges. Also, it is concluded that the classification of class 1 or compact section by EUROCODE 4 and AASHTO LRFD specifications is reasonable in negative moment regions of precast deck composite box girder bridges.
Rotter and Ansourian suggested the ductility parameter, which is defined as a ratio of a strain of concrete slabs and steel girders. In order to obtain a sufficient rotation and ductility of a composite section in positive moment regions, the strain of the steel section should be reached at strain hardening before the concrete is crushed. Therefore, the ductility parameter should be higher than unity such as,
In these experimental tests, ductility parameters of test specimens were evaluated. The ductility parameter of all specimens was higher than unity. The ductility parameter, χ of CBG1 was 1.38 and CBG2 was 1.73. In the test results, all specimens showed good ductility in positive moment regions of the ultimate state.Therefore,it is concluded that the Rotter ductility parameter could be used to estimate the ductility of precast deck composite box girder bridges properly. The differences of the parameter between CBG1 and CBG2 were due to the difference of concrete strength.
3.4. Numerical analysis
In order to estimate the ultimate behaviour of continuous composite bridges, an elastic–plastic finite element analysis program (EPACB: Elastic–Plastic Analysis for Composite Beams)was developed . The material nonlinearity was considered, as shown in Fig.6. In the steel ,strain hardening was considered and in the concrete of compression, the relationship suggested by Hognestad was used by modification of curve. Also, in the concrete of tension, the linear elastic curve was used below the tensile strength but over the tensile strength,a linear softening curve was assumed to account for the tension stiffening effects. There inforcement was modeled as a linear elastic and plastic curve in Fig. 6(c).
In this experimental study, local buckling did not occur until the full plastic moment had been reached and sufficient rotation had developed because the section classes of the specimens were all class 1. Also lateral torsional buckling did not occur because the composite box girder section has a high torsional stiffness. Therefore the specimens prevented from out-of-deflection due to buckling can be described by a Bernoulli beam theory until the maximum load. Thus, in numerical analysis, the continuous bridges could be described simply by one-dimensional beam elements using the Hermitian shape function. Also, it was assumed that the slip between the concrete slab and the steel girder did not occur thus the section behaved as a full composite section.
To set a material strength limit in the analysis, the tensile strength of concrete was determined by the introduced prestress at transverse joints and assumed bonding strength of 2 MPa. The compressive strength of concrete, strength of steel girder, reinforcement and tendon were determined from Tables1 and 2. Also, internal tendons were considered as reinforcement having equivalent diameter.
3.5. Load–deflection curve
Load–mid-span deflection curve of tests and analysis in CBG1 and CBG2 were described in Fig. 7. In an “elastic–plastic” curve in Fig.7, an initial linear curve was evaluated from the elastic analysis of three-dimensional finite element models. In this model,the concrete slab and the steel girder were modeled with four-node shell elements. The slab and the box girder were connected by rigid links because the model was assumed to behave as a full interaction. From the analysis, the flexural stiffness of the composite section could be evaluated as in Fig. 7. In the “elastic–plastic” curve, the horizontal curve was determined from the calculation by the mechanism thus the value is equal to the calculation in Table3. As shown in Fig.6, the numerical analysis predicted the test results well.
3.6. Moment–curvature curve
Moment–curvature curves of a maximum positive and a negative moment section are presented in Figs.8 and 9. It is shown that the analysis was similar to the test results. In the case of CBG1,the curve of numerical analysis(EPACB) is in good agreement with the curve of test results in Fig.8(a). From the results,it is concluded that the positive moment region of composite bridges with prefabricated slabs is uncracked, as in Fig.5(a). In a maximum negative moment region in Fig.8(b), the curve of the analysis was different from the initial curve of test results. It could be explained that the maximum negative moment section had already became almost a cracked section because the CBG1 had many loading cycles over the cracking load[8]. However,at a maximum moment level,the analysis was similar to the test results.
In addition, in case of CBG2, the curve of EPACB is consistent with the curve of the test results well. In a maximum negative moment region (Fig.9(b)),the analytical solution is very similar to the test results because the CBG2, unlike the CBG1, had only one cycle ultimate loading history after one cycle cracking load.Therefore,it could be observed that the flexural stiffness was decreased and became a cracked section with increasing loads.
From the results, it is considered that the numerical method in this study was very effective and thus in continuous composite box girder bridges with prefabricated slab, a cracked section could be assumed as the composition of girder, reinforcement, internal tendon or external tendon such as the numerical analysis and in Fig. 5 (b) or (c).
3.7. Moment redistributions
After cracking in negative moment regions, the real moment distribution of a continu-ous beam is not in agreement with the moment distribution calculated by the assumption of an uncracked composite section. After cracking and yielding of the composite section,the real moments in a continuous composite beam are redistributed.Therefore the real moment distribution could be evaluated from the numerical analysis considering material nonlin-earities. Using the program EPACB, the real moment distribution could be evaluated and then moment redistribution could be estimated.In EUROCODE4, it is defined that a ratio of moment redistribution is 15% by cracking and 40% in ultimate states for class1 section. From the nonlinear analysis which produced the above curve in Figs.8 and9 andTable5, it is concluded that the calculation for design by EUROCODE 4 is also similar or conservative to the results of nonlinear analysis, as shown in Table5. Also, the evaluation of the ultimate load by the plastic global analysis is similar to the results of the nonlinear analysis.
4. Conclusion
In this paper,in order to evaluate ultimate flexural strength,experimental and analytical studies of two-span continuous composite box-girder bridges with prefabricated slabs were conducted and from the results, it is concluded that:
(1) Eqs. (6)and(7) are effective in estimating the ultimate strength of shear connection and the degree of shear connection to obtain full shear connections.
(2) The rigid plastic analysis using the assumption of uncracked and cracked section for the positive and negative moment region respectively, could be applied to precast deck composite box girder bridges. Also,the classification of class1 or compact section by EUROCODE and AASHTO LRFD specifications are reasonable in negative moment regions of precast deck bridges.
(3) The Rotter ductility parameter could be used to estimate the ductility of precast deck bridges properly.
(4) It is considered that the numerical method in this study was very effective.
(5) If the composite section is class 1, the uncracked section method in EUROCODE 4 by the 15% moment redistribution after cracking and the 40% moment redistribution in ultimate states could be applied in continuous composite box-girder bridges with precast decks and in this case, the evaluation of the ultimate load by the plastic global analysis can be made efficiently.
中文翻译
预制桥面板连续组合箱形梁桥的极限强度
导言
预制混凝土板无论是对新建桥梁还是旧桥面板的替换都是非常具有吸引力的方案,因为预制系列能保证混凝土板的质量,改善工人们的工作环境,并减少施工时间和交通混乱。装配式桥梁有两种连接类型,钢梁与混凝土板的剪力连接以及预制板的横向连接。图1大体概述了在本文中涉及到的全纵深预制桥面组合桥梁。
在预制的组合式梁的研究上已经有过若干试验。通过对剪力连接的行为特点的观察,从压力试验的加载曲线中提出了一个关于连接的剪力刚度的经验公式。一个简单的大跨度组合梁上的弯曲疲劳试验显示了螺钉之间具有剪力重分配的能力。从这些研究结果,可以评价装配式组合桥的极限强度和螺钉剪力连接的疲劳耐力。
许多适用性问题,例如横向连接的开裂和渗水,有几个桥梁中已有
。预制桥梁桥面板在这一研究领域的研究表明最主要的问题是接缝的开裂。在这项研究中,预制板的横向接缝的节点除了纵向的内部筋没有别的钢筋。横向接缝没有设置钢筋的预制板面需要特别的照顾,并且板的设计应在服务荷载作用下防止接缝的开裂和渗漏。因此有必要在桥梁服务期间保持接缝处在压力状态以防止接缝开裂和渗漏。为此,在没有配置钢筋的接缝处防止裂缝的设计标准应该是这样的,当它处于服务荷载作用下时节点不允许拉应力出现。
为了调查研究预制桥面的桥梁的横向接缝的开裂特点开展了试验工作和分析研究。从这项研究,建议了几点设计时应考虑的事项。发生在接头的地方的拉应力对确定预应力是很重要的。节点顶部的压应力损失是可观的,应仔细评估以确定初始的张拉控制应力。很明显,降低由混凝土收缩产生的拉应力可以有效地减少预应力损失。预应力组合桥梁因为混凝土长期的行为产生的应力损失可能是不合算的,因此,预应力的优点例如浇注完预应力构件后的预加力时间也应在设计中考虑。
为了确定预制桥面的连续组合桥的设计基础理论已经做过无数的实验和分析。在这些研究中,进行连续组合梁的实验是为了观察连续梁的行为和验证拟定的防止节点裂缝的设计标准。在连续预制桥面板桥梁的节点处防止拉应力出现就足够了。
满足服务的极限状态的桥梁,也应该评估极限强度已界定极限状态。为了计算出组合部位的挠曲阻力,需要评估剪力连接的截面分类和概率。从以往的实验研究中得出的结论是,预制桥面板的桥梁的剪力连接器的极限强度成正比于螺钉螺柱的横截面面积而随着层间厚度的增加而减小。在本文中,进行了两跨连续组合箱形梁桥的实验与分析研究。评估了开裂、屈服和极限荷载,并同预制桥面板的连续组合桥的实验结果做了比较。为了评估连续梁桥的屈服荷载,考虑了一个不开裂截面的方法,该方法考虑了弯矩的重分配,在EUROCODE4对弯矩重分配下了定义。在极限强度的计算中,考虑了全部或部分剪力连接和截面种类,在EUROCODE4或者AASHTO LRFD的说明中对上述概念下了定义。同时,考虑材料的非线性,弯矩-曲率关系和弯矩重分配了通过数值分析进行了估计。
实验工作
2.1实例
对于中等跨径的桥梁,组合式箱形梁是很有吸引力的建设方案。可以考虑两种不同类型的箱梁——用全部封闭的钢结构做的箱梁和用“U”型部件做的箱梁。无论是哪一种,箱形截面可以是矩形或梯形。预制板可有效的应用于开放式钢箱梁桥因为可以免去混凝土浇筑成型的工作。在这方面的试验研究,建了一座连续组合式梯形“U”截面的箱形梁桥。
建了两座分别命名为CBG1和CBG2的装配式连续组合箱形梁桥。CBG1是10-10的两跨而CBG2是20-20的两跨连续梁桥。两个箱形梁桥具有一样的截面尺寸如图2(a)所示。在CBG的模型中,每个预制梁有6个为设置剪力连接器的挖空的块和5个40mm为后张法预留的管道。为了引入纵向预应力,5个直径15.2mm的预应力钢筋束穿过锚栓式锚碇安装在板上。此外,在CBG2中,在负弯矩区域的组合部分是在剪力连接后由外部钢筋施加预应力的(图2(c))。剪力连接器安装在主梁顶部法兰以实现充分的剪力连接。每个支撑上都放置了隔板并且额外在支撑间设置了K型支撑。内部钢框,纵向,水平和垂直的加筋都采用焊接。
参考EUROCODE3和EUROCODE4所建议的截面类别的范围,本试验模型的横断面分类如下。按照公式1在负弯矩的网状板的截面是第一类,而依照公式2在负弯矩区域的较低法兰的截面也是第一类。从AASHTO LRFD 规范出发,根据公式3和4负弯矩区域的网状板和低法兰截面都是压截面。作为组合箱形梁的结点应具有较高的抗扭刚度,以防止横向扭转屈曲并且具有足够的旋转能力。因此,极限荷载的计算可以采用塑性整体分析,并于实验相比较。
表示网板的高度,
表示网板的厚度,
是法兰的长度,
是法兰的厚度,而
表示塑性弯矩作用下网板的受压深度,
是受压法兰的指定最小屈服强度,
是受压法兰的宽度,而
是受压法兰的厚度。
2.2材料特性
钢材,混凝土和砂浆的材料特性分别列于表1和2。在CBG模型中用了5根钢筋束并且额外在CBG2模型中增加了两根外部钢筋。这些钢筋的面积和特性是相同的。
2.3实验步骤和尺寸
两个集中荷载由如图3所示的闭环电力液压测试仪MTS施加给中等跨度组合梁桥。在CBG1中,实施了为观察模型的弹性行为的静载实验随后实施了1000,000次循环的疲劳实验。这些实验过后,展开了研究组合梁桥开裂和非弹性行为的静载实验。在CBG2中,首先荷载加载至靠近内部支撑的部位的板出现第一条裂缝,然后后期荷载加载直至发展成大变形。
有关CBG模型的测量内容显示在图4中。用线性可变差动变压器(LVDTs;LV1;LV2)测量连续梁桥在每一个中大跨度的位移。也可安装LVDTs以测量钢筋和混凝土之间的相对位移如图4(SL1-SL2)所示。观察了混凝土板和钢梁(图4)部位A,B,C的应变。在CBG2中,为了摸清预应力变化,在外边钢筋束的锚固处放了两个荷载元件。
实验结果和分析
3.1全部或部分剪力连接
在测试模型中,事先为了实现充分的剪力连接安装了剪力连接器。一个剪力连接器的极限强度可以用Kim发明的公式5计算。
:剪力连接的极限强度,
:剪力连接部分的钢筋面积(
),
:铺盖层的厚度。
为了实现充分的剪力连接,剪力连接度,
定义为在剪力跨中的剪力连接器的强度,与全部剪力连接器的需求强度的一个比值,它应该要高于整体。
可以用公式5按在剪力板上计算,而
是混凝土或钢梁在全截面处于塑性弯矩时的水平力。
在CBG1和CBG2中,根据公式6预估的剪力连接度高于整体,然后再实验中,加之至极限荷载时最大误差达到1mm。从这个结果,有人认为剪力连接器不会达到极限荷载因此试验样本可能出现组合部位的全塑性弯矩状态。因此得出的结论是公式5和6在估计剪力连接器的极限强度和剪力连接度是有用的。
3.2开裂,屈服和极限荷载
先前的研究侧重于开裂荷载和开裂后的行为以加强预制板连续梁桥的适用性。在本次研究中,评估了开裂荷载,屈服荷载和极限荷载并同实验结果作了比较如表3所示。
在接近支撑的部位发生开裂之前,全跨的受力表现可看成不开裂构件,因此,可以估算出开裂荷载。在表3中,测试结果的开裂荷载均高于计算,因为忽略了横向板结点处的粘结力。为估算在最大正弯矩和最大负弯矩时的屈服和极限荷载,需要考虑弯矩的重分配。这是因为板的开裂和接近内部支撑处的主梁的屈服。由于裂缝和屈服,弯矩开始重分配,正弯矩增大,而负弯矩减少。实验中,屈服几乎同时发生在最大正弯矩和负弯矩的部位。
屈服荷载的计算采用的是不开裂构件使用的力矩重分配的计算方法。荷载加载到开裂荷载之后,负弯矩分配到正弯矩处有大约15﹪的弯矩使正弯矩区域出现屈服。据EUROCODE 4 ,40﹪的弯矩重分配可以被认为是1类截面的极限状态,但是,在塑性状态,预计会有发生更多的弯矩重分配。从表3 中,CBG1的计算结果表明和实验结果相接近。但是在实验结果中,正弯矩部位的屈服要比负弯矩屈服发生的要早。人们认为这要归结为残余应力。在CBG2中,计算有些低估了因为在屈服荷载的计算中忽略了外部钢筋束和锚固端。
计算极限荷载采用的是塑性力学的原理。因为实验样本在正弯矩和负弯矩范围内的截面分类全是第1类,因而有足够转换可以得到保证,可以使用塑性整体分析。在这个评价中,剪切影响并没有考虑因为这与弯曲结果相比是微不足道的。
表4列出了实验结果概率以及在开裂,屈服和极限荷载下的计算。从这些结果中,可以说。如果组合截面是第一类截面EURIOCODE 4中的开裂后15﹪弯矩重分配的不开裂方法和极限状态的40﹪力矩重分配可以应用于连续组合式预制板箱形梁桥,在这种情况下,评价极限荷载的塑性整体分析是有效的。
3.3塑性弯矩的评价
可以认为正弯矩部分是不开裂的而负弯矩部分是开裂的如图5所示。在CBG1中,在计算负弯矩部位(图5(b))的塑性弯矩时考虑了加固筋和内部钢筋。此外,在CBG2中,在计算如图5(c)的负弯矩部位的塑性弯矩是还考虑了外部钢筋。在这种情况下,负弯矩区段的塑性弯矩可以按以下公式计算:
: 构件n的屈服力;
:构件n到塑性中性轴的距离;
:加固;
:内部筋;
:上缘;
:受压板;
:外部筋;
:受拉状态的板;
:下缘。
因此,在如表3所示用原理计算极限荷载时,应用了对塑性弯矩的截面假设和公式7。在CBG1中,由于加载设备能力的缺乏,最高可观测量为1800KN。从测量的梁应变,构件A和C直至1800KN才完全屈服
。在CBG2中,尽管在实验中外部筋没有屈服,可以假定外部筋的轴力就是塑性分析中的屈服力。因此,根据原理计算的极限荷载在某种程度上被估高了。从表3中,可以得出,应用分别对应于正弯矩和负弯矩的开裂和不开裂的假设的塑性整体分析理论,可以应用在预制板组合箱梁桥。此外,可以得出结论是EUROCODE4和AASHTO LRFD 的规定中分类1或者说压截面的分类在预制板组合箱梁桥的负弯矩区域是合理的。
Rotter and Ansourian 提出了延性参数,定义为混凝土板和钢梁拉应力的比值。为了使正弯矩区域的组合截面获得足够的转动和延性,钢截面的应变应该在混凝土压碎以前达到应变硬化。因此,延性参数应该高于整体譬如,
是混凝土抗压强度,
是板的宽度,
是混凝土的极限压应变,
是板的深度,
是梁的深度,
是钢梁的截面面积,
是钢材的屈服荷载而
是硬化应变。
在实验结果中,对延性参数作了评价。所有试验样本的延性参数都高于整体。延性参数,CBG的χ为1.38而CBG2的χ为1.73。在测试结果中,所有样本的正弯矩区域在处于极限状态下都呈现良好的延性。因此,可以得出结论,Rotter延性参数可以用来正确地评估预制板组合梁桥的延性。CBG1和CBG2的参数的差别在于混凝土强度的不同。
3.4数学分析
为了评价连续组合梁桥的极限状态下的特性,开发了一个弹塑有限元分析程序(简称EPACB)。如图6所示,考虑了材料的非线性。对于钢材考虑了它的应变硬化,对于混凝土考虑了压缩,Hognestad提出两者之间的关系被用来修改了曲线。此外,在受拉的混凝土中,当低于拉力强度时采用线弹性曲线,当高于拉力强度时采用了线性锐化的曲线来计算拉力硬化效应。这些都转化成了如图6(c)所示的一个线性的弹性和塑性曲线。
在这方面的试验研究,局部屈曲直到达到全塑性弯矩和形成充分的转动才出现,因为所有样本的截面类别都是第1类。此外,横向扭转屈曲也没有出现,因为组合箱梁具有较高的扭转刚度。因此,实例中防止发生偏离归结为在达到最大荷载之前屈曲可以用Bernoulli 梁的理论来描述。因此,在数值分析中,可以把连续梁桥简单看作Hermitian几何函数表示的一维梁。此外,假设混凝土板和钢梁之间没有位移因此构件表现为一个整体的组合结构。
为了在分析中设定一个材料的强度限值,混凝土的抗拉强度由在横向接缝处的先期预加力决定并假定为2Mpa。混凝土的抗压强度,钢梁,加固筋和钢束的强度如表1和2中所示。此外,内部钢束在加固后按当量直径计算。
3.5荷载-位移 曲线
CBG1和CBG2的负载中跨度挠度曲线的测试与分析描述在图7中。在图7中的“弹-塑”曲线中,内部线性曲线是从三维有限元模型的弹性分析中得来的。在这个模型中,混凝土板和钢梁用四节点框架制作。板和箱梁用刚节点连接因为模型假定为一个整体。经分析,组合结构的挠曲刚度如图7。在“弹-塑”曲线中,水平曲线由同表3的计算原理计算决定。如图6所示,数字分析很好地预测测试结果。
3.6弯矩-曲率 曲线
最大正弯矩和负弯矩部分的弯矩-曲率曲线表示在图8和9内。表明分析接近于实验结果。在CBG1的情况中,数字分析的曲线(EPACB)和图8(a)的实验结果的曲线不是很吻合。从这个结果可以得出结论,预制板组合桥的正弯矩区域是不开裂的,如图5(a)。在图8(b)所示的最大负弯矩区域,分析曲线不同于实验结果的初始曲线。可以解释为最大负弯矩部分已经接近开裂因为CBG1的荷载循环次数超过了开裂荷载。然而,最大弯矩的分析和实验结果很接近。
此外,在CBG2的情况中,EPACB曲线和实验结果相一致。在最大负弯矩区域(图9(b)),分析结果和实验结果很相似因为CBG2,不同于CBG1,在加载一次开裂荷载后只有一个周期的极限荷载。因此,可以观察到挠曲刚度下降并且开裂部分荷载增加。
从结果可得,数值计算方法在本项研究中非常有效,因此在连续组合预制板式箱梁桥中,开裂部位可以假定如图5(b)或(c)中对梁,加固筋,外部钢束或内部钢束组合的计算。
3.7弯矩重分配
在负弯矩部位开裂后,连续梁的实际力矩重分配和由不开裂组合构件的假定计算的力矩重分配是不一样的。在组合部位开裂和屈服后,在连续组合梁中的真实弯矩发生重分配。因此真正的力矩重分配可以从考虑材料的非线性的数值分析评估。用EPACB程序,真正的力矩分配可以估计然后评价。在EUROCODE4中,定义力矩重分配度为开裂的15%和1类截面极限状态时的40%。从生成如图8和9以及表5的曲线的非线性分析中得出的结论认为,依照EUROCODE4的计算相似于或等同非线性分析的结果,如表5所示。此外,采用塑性整体分析计算的极限荷载的评估接近于非线性分析的结果。
4.结论
在本文中,为了评估极限挠曲强度,开展了对两跨连续组合预制板箱梁桥的实验和分析研究,得出的结论是:
(1)公式6和7在估计剪力连接的极限强度和剪力连接器度时以获得全面的剪力连接时是非常有效的。
(2)采用对正弯矩和负弯矩区域分别按不开裂和开裂的假设的刚塑性分析,可以应用在预制板组合箱梁桥。此外,EUROCODE和AASHTO LRFD规范定义的1类或受压截面的分类在预制桥面板的桥梁中是合理的。
(3)Rotter 延性参数可以用来正确的估计预制甲板的延性。
(4)在本研究的数字方法是非常有效的。
(5)假设组合截面是第1类截面,按EUROCODE4规定的不开裂截面在开裂后按15%而在极限状态按40%力矩重分配,可以应用于连续组合预制面板箱梁桥,在这种情况下,按塑性整体分析所评估的极限荷载是有效的。
L=38.88
P/2 P/2 P/2 P/2
图5 跨中的横向分布系数mc计算图式(尺寸单位:mm)
0.2 0.2 0.2 0.2
0.3641 0.2662 0.1355 0.0476
1号梁
2号梁
3号梁
0.5264 0.3306 .01891 -0.0067
人群
2号梁
0.75
0.125
0.875
1号梁
0.25
0.9375
3号梁
0.4375
1.429
0.5197
0.6216
0.75
1.0
0.047
0.0965
0.953
0.047
1.96
0.515
人群 m
汽车 m
支点影响线 V
M
变化点影响线
V
V
四分点影响线
M
V
跨中影响线
M
3L/16
1.545
0.047
0.75
0.25
L/4
0.047
0.5
0.5
图7 跨中截面作用效应计算图式
a b
支座中线
X1
X
X2
O
R
计算截面位置
c
a0
起弯点
主梁底面线
a 1
跨径中线
锚固点
①
②
③
⑥
⑤
④
b
a
X
垫板1
垫板2
L=4388cm
q人=2.25kn/m
公路车辆荷载
1.0
0.8724
-1.3117
-0.6318
0.9223
0.2876
-0.4882
P/2 P/2
P/2 P/2
人群
人群
1.2443
0.6878
0.9658
0.1760
-1.0698
0.0067
0.3306
0.1782
0.5264
P/2 P/2 P/2 P/2
P/2 P/2 P/2 P/2
0.40
0.6841
0.3543
0.2074
-0.1223
Q右2影响线
Q右1影响线
MB影响线
MA影响线
2� EMBED Equation.3 ���20
4� EMBED Equation.3 ���20
图 21车辆荷载在板上的分布
� EMBED Equation.DSMT4 ���
� EMBED Equation.DSMT4 ���
� EMBED Equation.DSMT4 ���
� EMBED Equation.DSMT4 ���
� EMBED Equation.DSMT4 ���
� EMBED Equation.DSMT4 ���
� EMBED Equation.DSMT4 ���
图22行车道板受力钢筋布置图示(尺寸单位:mm)
� EMBED \* MERGEFORMAT ���
_1234568145.unknown
_1234568273.unknown
_1234568401.unknown
_1234568465.unknown
_1234568497.unknown
_1234568529.unknown
_1234568545.unknown
_1234568561.unknown
_1234568569.unknown
_1234568577.unknown
_1234568581.unknown
_1234568585.unknown
_1234568587.unknown
_1234568589.unknown
_1234568591.unknown
_1234568592.unknown
_1234568590.unknown
_1234568588.unknown
_1234568586.unknown
_1234568583.unknown
_1234568584.unknown
_1234568582.unknown
_1234568579.unknown
_1234568580.unknown
_1234568578.unknown
_1234568573.unknown
_1234568575.unknown
_1234568576.unknown
_1234568574.unknown
_1234568571.unknown
_1234568572.unknown
_1234568570.unknown
_1234568565.unknown
_1234568567.unknown
_1234568568.unknown
_1234568566.unknown
_1234568563.unknown
_1234568564.unknown
_1234568562.unknown
_1234568553.unknown
_1234568557.unknown
_1234568559.dwg
_1234568560.unknown
_1234568558.unknown
_1234568555.unknown
_1234568556.unknown
_1234568554.unknown
_1234568549.unknown
_1234568551.unknown
_1234568552.unknown
_1234568550.unknown
_1234568547.unknown
_1234568548.unknown
_1234568546.unknown
_1234568537.unknown
_1234568541.unknown
_1234568543.unknown
_1234568544.unknown
_1234568542.unknown
_1234568539.unknown
_1234568540.unknown
_1234568538.unknown
_1234568533.unknown
_1234568535.unknown
_1234568536.unknown
_1234568534.unknown
_1234568531.unknown
_1234568532.unknown
_1234568530.dwg
_1234568513.unknown
_1234568521.unknown
_1234568525.unknown
_1234568527.unknown
_1234568528.unknown
_1234568526.unknown
_1234568523.unknown
_1234568524.unknown
_1234568522.unknown
_1234568517.unknown
_1234568519.dwg
_1234568520.unknown
_1234568518.dwg
Administrator
_1234568515.unknown
_1234568516.unknown
_1234568514.unknown
_1234568505.unknown
_1234568509.unknown
_1234568511.unknown
_1234568512.unknown
_1234568510.unknown
_1234568507.unknown
_1234568508.unknown
_1234568506.unknown
_1234568501.unknown
_1234568503.unknown
_1234568504.unknown
_1234568502.unknown
_1234568499.unknown
_1234568500.unknown
_1234568498.dwg
_1234568481.unknown
_1234568489.unknown
_1234568493.unknown
_1234568495.unknown
_1234568496.unknown
_1234568494.unknown
_1234568491.unknown
_1234568492.unknown
_1234568490.unknown
_1234568485.unknown
_1234568487.unknown
_1234568488.unknown
_1234568486.unknown
_1234568483.unknown
_1234568484.unknown
_1234568482.unknown
_1234568473.unknown
_1234568477.unknown
_1234568479.unknown
_1234568480.unknown
_1234568478.unknown
_1234568475.unknown
_1234568476.unknown
_1234568474.unknown
_1234568469.unknown
_1234568471.unknown
_1234568472.unknown
_1234568470.unknown
_1234568467.unknown
_1234568468.unknown
_1234568466.unknown
_1234568433.unknown
_1234568449.unknown
_1234568457.unknown
_1234568461.unknown
_1234568463.unknown
_1234568464.unknown
_1234568462.unknown
_1234568459.unknown
_1234568460.unknown
_1234568458.unknown
_1234568453.unknown
_1234568455.unknown
_1234568456.unknown
_1234568454.unknown
_1234568451.unknown
_1234568452.unknown
_1234568450.unknown
_1234568441.unknown
_1234568445.unknown
_1234568447.unknown
_1234568448.unknown
_1234568446.unknown
_1234568443.unknown
_1234568444.unknown
_1234568442.dwg
_1234568437.unknown
_1234568439.unknown
_1234568440.unknown
_1234568438.unknown
_1234568435.unknown
_1234568436.unknown
_1234568434.unknown
_1234568417.unknown
_1234568425.unknown
_1234568429.unknown
_1234568431.unknown
_1234568432.unknown
_1234568430.unknown
_1234568427.unknown
_1234568428.unknown
_1234568426.unknown
_1234568421.unknown
_1234568423.unknown
_1234568424.unknown
_1234568422.unknown
_1234568419.unknown
_1234568420.unknown
_1234568418.unknown
_1234568409.unknown
_1234568413.unknown
_1234568415.unknown
_1234568416.unknown
_1234568414.unknown
_1234568411.unknown
_1234568412.unknown
_1234568410.unknown
_1234568405.unknown
_1234568407.unknown
_1234568408.unknown
_1234568406.unknown
_1234568403.unknown
_1234568404.unknown
_1234568402.unknown
_1234568337.unknown
_1234568369.unknown
_1234568385.unknown
_1234568393.unknown
_1234568397.unknown
_1234568399.unknown
_1234568400.unknown
_1234568398.unknown
_1234568395.unknown
_1234568396.unknown
_1234568394.unknown
_1234568389.unknown
_1234568391.unknown
_1234568392.unknown
_1234568390.unknown
_1234568387.unknown
_1234568388.unknown
_1234568386.unknown
_1234568377.unknown
_1234568381.unknown
_1234568383.unknown
_1234568384.unknown
_1234568382.unknown
_1234568379.unknown
_1234568380.unknown
_1234568378.unknown
_1234568373.unknown
_1234568375.unknown
_1234568376.unknown
_1234568374.unknown
_1234568371.unknown
_1234568372.unknown
_1234568370.unknown
_1234568353.unknown
_1234568361.unknown
_1234568365.unknown
_1234568367.unknown
_1234568368.unknown
_1234568366.unknown
_1234568363.unknown
_1234568364.unknown
_1234568362.unknown
_1234568357.unknown
_1234568359.unknown
_1234568360.unknown
_1234568358.unknown
_1234568355.unknown
_1234568356.unknown
_1234568354.unknown
_1234568345.unknown
_1234568349.unknown
_1234568351.unknown
_1234568352.unknown
_1234568350.unknown
_1234568347.unknown
_1234568348.unknown
_1234568346.dwg
_1234568341.unknown
_1234568343.unknown
_1234568344.unknown
_1234568342.unknown
_1234568339.unknown
_1234568340.unknown
_1234568338.unknown
_1234568305.unknown
_1234568321.unknown
_1234568329.unknown
_1234568333.unknown
_1234568335.unknown
_1234568336.unknown
_1234568334.unknown
_1234568331.unknown
_1234568332.unknown
_1234568330.unknown
_1234568325.unknown
_1234568327.unknown
_1234568328.unknown
_1234568326.unknown
_1234568323.unknown
_1234568324.unknown
_1234568322.unknown
_1234568313.unknown
_1234568317.unknown
_1234568319.unknown
_1234568320.unknown
_1234568318.unknown
_1234568315.unknown
_1234568316.unknown
_1234568314.unknown
_1234568309.unknown
_1234568311.unknown
_1234568312.unknown
_1234568310.unknown
_1234568307.unknown
_1234568308.unknown
_1234568306.unknown
_1234568289.unknown
_1234568297.unknown
_1234568301.unknown
_1234568303.unknown
_1234568304.unknown
_1234568302.unknown
_1234568299.unknown
_1234568300.unknown
_1234568298.unknown
_1234568293.unknown
_1234568295.unknown
_1234568296.unknown
_1234568294.unknown
_1234568291.unknown
_1234568292.unknown
_1234568290.unknown
_1234568281.unknown
_1234568285.unknown
_1234568287.unknown
_1234568288.unknown
_1234568286.unknown
_1234568283.unknown
_1234568284.unknown
_1234568282.unknown
_1234568277.unknown
_1234568279.unknown
_1234568280.unknown
_1234568278.unknown
_1234568275.unknown
_1234568276.unknown
_1234568274.unknown
_1234568209.unknown
_1234568241.unknown
_1234568257.unknown
_1234568265.unknown
_1234568269.unknown
_1234568271.unknown
_1234568272.unknown
_1234568270.unknown
_1234568267.unknown
_1234568268.unknown
_1234568266.unknown
_1234568261.unknown
_1234568263.unknown
_1234568264.unknown
_1234568262.unknown
_1234568259.unknown
_1234568260.unknown
_1234568258.unknown
_1234568249.unknown
_1234568253.unknown
_1234568255.unknown
_1234568256.unknown
_1234568254.unknown
_1234568251.unknown
_1234568252.unknown
_1234568250.unknown
_1234568245.unknown
_1234568247.unknown
_1234568248.unknown
_1234568246.unknown
_1234568243.unknown
_1234568244.unknown
_1234568242.unknown
_1234568225.unknown
_1234568233.unknown
_1234568237.unknown
_1234568239.unknown
_1234568240.unknown
_1234568238.unknown
_1234568235.unknown
_1234568236.unknown
_1234568234.unknown
_1234568229.unknown
_1234568231.unknown
_1234568232.unknown
_1234568230.unknown
_1234568227.unknown
_1234568228.unknown
_1234568226.unknown
_1234568217.unknown
_1234568221.unknown
_1234568223.unknown
_1234568224.unknown
_1234568222.unknown
_1234568219.unknown
_1234568220.unknown
_1234568218.unknown
_1234568213.unknown
_1234568215.unknown
_1234568216.unknown
_1234568214.unknown
_1234568211.unknown
_1234568212.unknown
_1234568210.unknown
_1234568177.unknown
_1234568193.dwg
_1234568201.unknown
_1234568205.unknown
_1234568207.unknown
_1234568208.unknown
_1234568206.unknown
_1234568203.unknown
_1234568204.unknown
_1234568202.unknown
_1234568197.unknown
_1234568199.unknown
_1234568200.unknown
_1234568198.unknown
_1234568195.unknown
_1234568196.unknown
_1234568194.unknown
_1234568185.unknown
_1234568189.unknown
_1234568191.unknown
_1234568192.unknown
_1234568190.unknown
_1234568187.unknown
_1234568188.unknown
_1234568186.unknown
_1234568181.unknown
_1234568183.unknown
_1234568184.unknown
_1234568182.unknown
_1234568179.unknown
_1234568180.unknown
_1234568178.unknown
_1234568161.unknown
_1234568169.unknown
_1234568173.unknown
_1234568175.unknown
_1234568176.unknown
_1234568174.unknown
_1234568171.unknown
_1234568172.unknown
_1234568170.unknown
_1234568165.unknown
_1234568167.unknown
_1234568168.unknown
_1234568166.unknown
_1234568163.unknown
_1234568164.unknown
_1234568162.unknown
_1234568153.unknown
_1234568157.unknown
_1234568159.unknown
_1234568160.unknown
_1234568158.unknown
_1234568155.unknown
_1234568156.unknown
_1234568154.unknown
_1234568149.unknown
_1234568151.unknown
_1234568152.unknown
_1234568150.unknown
_1234568147.unknown
_1234568148.unknown
_1234568146.unknown
_1234568017.unknown
_1234568081.unknown
_1234568113.unknown
_1234568129.unknown
_1234568137.unknown
_1234568141.unknown
_1234568143.unknown
_1234568144.unknown
_1234568142.unknown
_1234568139.unknown
_1234568140.unknown
_1234568138.unknown
_1234568133.unknown
_1234568135.unknown
_1234568136.unknown
_1234568134.unknown
_1234568131.unknown
_1234568132.unknown
_1234568130.unknown
_1234568121.unknown
_1234568125.unknown
_1234568127.unknown
_1234568128.unknown
_1234568126.unknown
_1234568123.unknown
_1234568124.unknown
_1234568122.unknown
_1234568117.unknown
_1234568119.unknown
_1234568120.unknown
_1234568118.unknown
_1234568115.unknown
_1234568116.unknown
_1234568114.unknown
_1234568097.unknown
_1234568105.unknown
_1234568109.unknown
_1234568111.unknown
_1234568112.unknown
_1234568110.unknown
_1234568107.unknown
_1234568108.unknown
_1234568106.unknown
_1234568101.unknown
_1234568103.unknown
_1234568104.unknown
_1234568102.unknown
_1234568099.unknown
_1234568100.unknown
_1234568098.unknown
_1234568089.unknown
_1234568093.unknown
_1234568095.unknown
_1234568096.unknown
_1234568094.unknown
_1234568091.unknown
_1234568092.unknown
_1234568090.unknown
_1234568085.unknown
_1234568087.unknown
_1234568088.unknown
_1234568086.dwg
_1234568083.unknown
_1234568084.unknown
_1234568082.unknown
_1234568049.unknown
_1234568065.unknown
_1234568073.unknown
_1234568077.unknown
_1234568079.unknown
_1234568080.unknown
_1234568078.unknown
_1234568075.unknown
_1234568076.unknown
_1234568074.unknown
_1234568069.unknown
_1234568071.unknown
_1234568072.unknown
_1234568070.unknown
_1234568067.dwg
_1234568068.unknown
_1234568066.dwg
_1234568057.unknown
_1234568061.dwg
park
_1234568063.unknown
_1234568064.unknown
_1234568062.dwg
_1234568059.unknown
_1234568060.unknown
_1234568058.unknown
_1234568053.unknown
_1234568055.unknown
_1234568056.unknown
_1234568054.dwg
_1234568051.unknown
_1234568052.unknown
_1234568050.unknown
_1234568033.unknown
_1234568041.unknown
_1234568045.unknown
_1234568047.unknown
_1234568048.unknown
_1234568046.unknown
_1234568043.unknown
_1234568044.unknown
_1234568042.unknown
_1234568037.unknown
_1234568039.unknown
_1234568040.unknown
_1234568038.unknown
_1234568035.unknown
_1234568036.unknown
_1234568034.unknown
_1234568025.unknown
_1234568029.unknown
_1234568031.unknown
_1234568032.unknown
_1234568030.unknown
_1234568027.unknown
_1234568028.unknown
_1234568026.unknown
_1234568021.unknown
_1234568023.unknown
_1234568024.unknown
_1234568022.unknown
_1234568019.unknown
_1234568020.unknown
_1234568018.unknown
_1234567953.unknown
_1234567985.unknown
_1234568001.unknown
_1234568009.unknown
_1234568013.unknown
_1234568015.unknown
_1234568016.unknown
_1234568014.unknown
_1234568011.unknown
_1234568012.unknown
_1234568010.unknown
_1234568005.unknown
_1234568007.unknown
_1234568008.unknown
_1234568006.unknown
_1234568003.unknown
_1234568004.unknown
_1234568002.dwg
_1234567993.dwg
_1234567997.unknown
_1234567999.unknown
_1234568000.unknown
_1234567998.unknown
_1234567995.unknown
_1234567996.unknown
_1234567994.unknown
_1234567989.unknown
_1234567991.unknown
_1234567992.unknown
_1234567990.unknown
_1234567987.unknown
_1234567988.unknown
_1234567986.dwg
_1234567969.unknown
_1234567977.unknown
_1234567981.unknown
_1234567983.unknown
_1234567984.unknown
_1234567982.unknown
_1234567979.unknown
_1234567980.unknown
_1234567978.unknown
_1234567973.unknown
_1234567975.unknown
_1234567976.unknown
_1234567974.unknown
_1234567971.unknown
_1234567972.unknown
_1234567970.unknown
_1234567961.unknown
_1234567965.unknown
_1234567967.unknown
_1234567968.unknown
_1234567966.unknown
_1234567963.unknown
_1234567964.dwg
_1234567962.unknown
_1234567957.unknown
_1234567959.unknown
_1234567960.unknown
_1234567958.unknown
_1234567955.unknown
_1234567956.unknown
_1234567954.unknown
_1234567921.dwg
_1234567937.unknown
_1234567945.unknown
_1234567949.unknown
_1234567951.unknown
_1234567952.unknown
_1234567950.unknown
_1234567947.unknown
_1234567948.unknown
_1234567946.unknown
_1234567941.unknown
_1234567943.unknown
_1234567944.unknown
_1234567942.unknown
_1234567939.unknown
_1234567940.unknown
_1234567938.unknown
_1234567929.unknown
_1234567933.unknown
_1234567935.unknown
_1234567936.unknown
_1234567934.unknown
_1234567931.unknown
_1234567932.unknown
_1234567930.unknown
_1234567925.unknown
_1234567927.unknown
_1234567928.unknown
_1234567926.unknown
_1234567923.dwg
_1234567924.unknown
_1234567922.dwg
_1234567905.unknown
_1234567913.unknown
_1234567917.unknown
_1234567919.unknown
_1234567920.unknown
_1234567918.unknown
_1234567915.unknown
_1234567916.unknown
_1234567914.unknown
_1234567909.unknown
_1234567911.unknown
_1234567912.unknown
_1234567910.unknown
_1234567907.unknown
_1234567908.unknown
_1234567906.unknown
_1234567897.unknown
_1234567901.unknown
_1234567903.unknown
_1234567904.unknown
_1234567902.unknown
_1234567899.unknown
_1234567900.unknown
_1234567898.unknown
_1234567893.unknown
_1234567895.unknown
_1234567896.unknown
_1234567894.unknown
_1234567891.unknown
_1234567892.unknown
_1234567890.unknown